East Central RailwayIn Progress

Earthwork in embankment, Blanketing work, construction of minor bridges, RUB's, Retaining wall, Height gauge, approach road etc. from Madhubani Yard (excl) to Areraj yard (incl.) in connection with construction of Hajipur-Sagauli new rail line project

Estimate Cost

₹146.38 Cr

Sanctioned estimate

Tendered Cost

₹136.94 Cr

-6.4% vs estimate

Physical Progress

16%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹136.94 Cr
Progress16%
Started27-02-2024
Target DOC31-07-2027
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
293
Agency
Lall Construction India Limited-New Delhi, Third Floor
Plot No. 28, Karuna Kunj, Sector 03 Dwarka, New Delhi-110075
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-57-23-24 / 00866770098478 dt 27.02.25
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹146.38 Cr
Tendered Cost
₹136.94 Cr
Physical Progress
16%
Date Started
27-02-2024
Original DOC
27-11-2025
Extended DOC
31-07-2027

Earthwork in embankment, Blanketing work, construction of minor bridges, RUB's, Retaining wall, Height gauge, approach road etc. from Madhubani Yard (excl) to Areraj yard (incl.) in connection with construction of Hajipur-Sagauli new rail line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by Lall Construction India Limited-New Delhi. The tendered cost of the work is ₹136.94 Cr, and it is currently In Progress with physical progress recorded at 16%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment, Blanketing work, construction of minor bridges, RUB's, "?
Status: In Progress. This East Central Railway work is being executed by Lall Construction India Limited-New Delhi. Physical progress stands at 16%. Current date of completion (DOC): 31-07-2027.
QWho is the agency for this Bihar railway project?
The agency for this work is Lall Construction India Limited-New Delhi, Third Floor, Plot No. 28, Karuna Kunj, Sector 03 Dwarka, New Delhi-110075. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-57-23-24 / 00866770098478 dt 27.02.25. Work started on 27-02-2024.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment, Blanketing work, construction of mi" is ₹136.94 Cr (against an estimate of ₹146.38 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, Blanketing work, construction of mi" is one of hundreds of railway works covered.