East Central RailwayOverdue

Earth work in embankment, blanketing, retaining wall, costruction of minor bridges between KBP (excl.) to VKNR (encl.) section, i.e. Km: 278/11 to Km: 296/11 in connection with doubling of Narkatiaganj-Valmikinagar Road section.

Work #139
As of March 2026

Estimate Cost

₹58.89 Cr

Sanctioned estimate

Tendered Cost

₹67.47 Cr

+14.6% vs estimate

Physical Progress

95%

Work completed

Status

Overdue

Current stage

East Central Railway — CAO (Con)Overdue
Tendered₹67.47 Cr
Progress95%
Started08-02-2019
Target DOC31-03-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE

Work Details

5 Fields
Work No.
139
Agency
Fulena Construction (P) Ltd
Sri Krishna Nagar, Begusarai-851101
Acceptance / LOA
LOA No ECR/CAO/Con/North/ETN-60-18-19 dt. 08.01.2019
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹58.89 Cr
Tendered Cost
₹67.47 Cr
Physical Progress
95%
Date Started
08-02-2019
Original DOC
31-03-2026
Extended DOC
N/A

Earth work in embankment, blanketing, retaining wall, costruction of minor bridges between KBP (excl.) to VKNR (encl.) section, i.e. Km: 278/11 to Km: 296/11 in connection with doubling of Narkatiaganj-Valmikinagar Road section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Fulena Construction (P) Ltd.. The tendered cost of the work is ₹67.47 Cr, and it is currently Overdue with physical progress recorded at 95%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earth work in embankment, blanketing, retaining wall, costruction of minor bridg"?
Status: Overdue. This East Central Railway work is being executed by Fulena Construction (P) Ltd.. Physical progress stands at 95%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Fulena Construction (P) Ltd., Sri Krishna Nagar, Begusarai-851101. Acceptance / agreement reference: LOA No ECR/CAO/Con/North/ETN-60-18-19 dt. 08.01.2019. Work started on 08-02-2019.
QWhat is the cost of this railway work?
The tendered cost of "Earth work in embankment, blanketing, retaining wall, costru" is ₹67.47 Cr (against an estimate of ₹58.89 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earth work in embankment, blanketing, retaining wall, costru" is one of hundreds of railway works covered.