East Central RailwayFinal Bill / Closure

Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and other allied misc. works between Supaul station (Excl.) to Pipra station (Incl.) i:e Km 73.000 to Km 95.556 in connection with construction of new B.G. rail line between Ararai-Supaul.

Work #43
As of March 2026

Estimate Cost

₹172.54 Cr

Sanctioned estimate

Tendered Cost

₹179.03 Cr

+3.8% vs estimate

Physical Progress

95%

Work completed

Status

Final Bill / Closure

Current stage

East Central Railway — CAO (Con)Final Bill / Closure
Tendered₹179.03 Cr
Progress95%
Started19-09-2020
Target DOC31-10-2025
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG

Work Details

5 Fields
Work No.
43
Acceptance / LOA
ECR-CAO-C-N-ETN-98-19-20/10271780018932 Dated 11.05.2020 ECR/CAO/Con/WT/Agt/152 Dtd. 04.02.2021
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹172.54 Cr
Tendered Cost
₹179.03 Cr
Physical Progress
95%
Date Started
19-09-2020
Original DOC
31-10-2025
Extended DOC
N/A

Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and other allied misc. works between Supaul station (Excl.) to Pipra station (Incl.) i:e Km 73.000 to Km 95.556 in connection with construction of new B.G. rail line between Ararai-Supaul. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S VKJ-JPW JV. The tendered cost of the work is ₹179.03 Cr, and it is currently Final Bill / Closure with physical progress recorded at 95%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work completed. Final variation is under process.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and"?
Status: Final Bill / Closure. This East Central Railway work is being executed by M/S VKJ-JPW JV. Physical progress stands at 95%. Current date of completion (DOC): 31-10-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is M/S VKJ-JPW JV. Acceptance / agreement reference: ECR-CAO-C-N-ETN-98-19-20/10271780018932 Dated 11.05.2020 ECR/CAO/Con/WT/Agt/152 Dtd. 04.02.2021. Work started on 19-09-2020.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment, blanketing, construction of minor b" is ₹179.03 Cr (against an estimate of ₹172.54 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, blanketing, construction of minor b" is one of hundreds of railway works covered.