East Central RailwayIn Progress

Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and other allied misc. works between Baghaily halt (incl.) to Jadia station (excl.) i.e. from Km 44.0 to Km 51.80 in connection with construction of new B.G. rail line between Arariaa-Supaul.

Estimate Cost

₹89.61 Cr

Sanctioned estimate

Tendered Cost

₹77.91 Cr

-13.1% vs estimate

Physical Progress

17%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹77.91 Cr
Progress17%
Started22-04-2025
Target DOC30-06-2026
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG

Work Details

5 Fields
Work No.
64
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-47-23-24/10130830103519
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹89.61 Cr
Tendered Cost
₹77.91 Cr
Physical Progress
17%
Date Started
22-04-2025
Original DOC
30-06-2026
Extended DOC
N/A

Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and other allied misc. works between Baghaily halt (incl.) to Jadia station (excl.) i.e. from Km 44.0 to Km 51.80 in connection with construction of new B.G. rail line between Arariaa-Supaul. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Raj Kumar Singh Raja Construction Private Limited-Patna. The tendered cost of the work is ₹77.91 Cr, and it is currently In Progress with physical progress recorded at 17%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment, blanketing, construction of minor bridges, RUB, LHS and"?
Status: In Progress. This East Central Railway work is being executed by M/s Raj Kumar Singh Raja Construction Private Limited-Patna. Physical progress stands at 17%. Current date of completion (DOC): 30-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Raj Kumar Singh Raja Construction Private Limited-Patna. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-47-23-24/10130830103519. Work started on 22-04-2025.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment, blanketing, construction of minor b" is ₹77.91 Cr (against an estimate of ₹89.61 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, blanketing, construction of minor b" is one of hundreds of railway works covered.