East Central RailwayIn Progress

E-Tender no. ECR-CAO-Con-N-E-tender-47-19-20 for the work of Linking of BG track including dismantling BG track, transportation of P-way material, carting & stacking released materials, Unloading and spreadinf of ballast, 60 kg rails etc. other ancillary & miscllaneouse works in c/w doubling of Sagauli-Narkatiaganj section.

Work #127
As of March 2026

Estimate Cost

₹15.76 Cr

Sanctioned estimate

Tendered Cost

₹19.36 Cr

+22.8% vs estimate

Physical Progress

98%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹19.36 Cr
Progress98%
Started15-01-2020
Target DOC31-03-2026
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH

Work Details

5 Fields
Work No.
127
Agency
Brijnandan Singh Triveni A
Flat No.1 DHristinagar, Asansol West Bengal.
Acceptance / LOA
ECR/CAO/Con/WT/Agt/114 dated. 27.08.2020.
Officer in Charge
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹15.76 Cr
Tendered Cost
₹19.36 Cr
Physical Progress
98%
Date Started
15-01-2020
Original DOC
14-01-2022
Extended DOC
31-03-2026

E-Tender no. ECR-CAO-Con-N-E-tender-47-19-20 for the work of Linking of BG track including dismantling BG track, transportation of P-way material, carting & stacking released materials, Unloading and spreadinf of ballast, 60 kg rails etc. other ancillary & miscllaneouse works in c/w doubling of Sagauli-Narkatiaganj section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Brijnandan Singh Triveni A. The tendered cost of the work is ₹19.36 Cr, and it is currently In Progress with physical progress recorded at 98%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "E-Tender no. ECR-CAO-Con-N-E-tender-47-19-20 for the work of Linking of BG track"?
Status: In Progress. This East Central Railway work is being executed by Brijnandan Singh Triveni A. Physical progress stands at 98%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Brijnandan Singh Triveni A, Flat No.1 DHristinagar, Asansol West Bengal.. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt/114 dated. 27.08.2020.. Work started on 15-01-2020.
QWhat is the cost of this railway work?
The tendered cost of "E-Tender no. ECR-CAO-Con-N-E-tender-47-19-20 for the work of" is ₹19.36 Cr (against an estimate of ₹15.76 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "E-Tender no. ECR-CAO-Con-N-E-tender-47-19-20 for the work of" is one of hundreds of railway works covered.