East Central RailwayOverdue

Balance work of construction of Signal and telecom complex building at Khagaria, earthwork in embankment, sub bank and ditches near toe of formation & other miscellaneous work from Km. 0.00 to Km 10.00 in connection with Khagaria-Kusheshwar Asthan New BG Rail Line project.

Work #192
As of June 2026

Estimate Cost

₹7.42 Cr

Sanctioned estimate

Tendered Cost

₹6.58 Cr

-11.3% vs estimate

Physical Progress

81%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹6.58 Cr
Progress81%
Started02-01-2018
Target DOC31-12-2025
Mahboob Alam, CE/C/NC/MHX; Avinash Sahani, Dy.CE/C/II/SPJ

Work Details

5 Fields
Work No.
192
Agency
Swata Construction
At & PO-Bihat, Tola Khemkaranpur, Begusarai, Bihar-8551135
Acceptance / LOA
01.12.2017 / ECR/CAO/Con/WT/Agt/39 dt. 14.02.18
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Avinash Sahani, Dy.CE/C/II/SPJ
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹7.42 Cr
Tendered Cost
₹6.58 Cr
Physical Progress
81%
Date Started
02-01-2018
Original DOC
31-12-2025
Extended DOC
N/A

Balance work of construction of Signal and telecom complex building at Khagaria, earthwork in embankment, sub bank and ditches near toe of formation & other miscellaneous work from Km. 0.00 to Km 10.00 in connection with Khagaria-Kusheshwar Asthan New BG Rail Line project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Swata Construction. The tendered cost of the work is ₹6.58 Cr, and it is currently Overdue with physical progress recorded at 81%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 6.58/9.50

?

Frequently Asked Questions

QWhat is the current status of the railway work "Balance work of construction of Signal and telecom complex building at Khagaria,"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/s Swata Construction. Physical progress stands at 81%. Current date of completion (DOC): 31-12-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Swata Construction, At & PO-Bihat, Tola Khemkaranpur, Begusarai, Bihar-8551135. Acceptance / agreement reference: 01.12.2017 / ECR/CAO/Con/WT/Agt/39 dt. 14.02.18. Work started on 02-01-2018.
QWhat is the cost of this railway work?
The tendered cost of "Balance work of construction of Signal and telecom complex b" is ₹6.58 Cr (against an estimate of ₹7.42 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Balance work of construction of Signal and telecom complex b" is one of hundreds of railway works covered.