East Central RailwayIn Progress

Balance earthwork, Blanketing work in embankment and construction of minor bridges/RUBs from Sahebganj to Madhubani in connection with construction of Hajipur-Sagauli new BG rail line project.

Estimate Cost

₹89.48 Cr

Sanctioned estimate

Tendered Cost

₹78.61 Cr

-12.1% vs estimate

Physical Progress

34%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹78.61 Cr
Progress34%
Started27-05-2024
Target DOC31-12-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
294
Agency
GVV Constructions Private Limited-Bhubaneswar
Plot No 358 Saheed Nagar, Bhubaneswar, Odisha-751007, India
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-02-24-25 / 00910690103878 dt 27.05.24
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹89.48 Cr
Tendered Cost
₹78.61 Cr
Physical Progress
34%
Date Started
27-05-2024
Original DOC
27-05-2025
Extended DOC
31-12-2026

Balance earthwork, Blanketing work in embankment and construction of minor bridges/RUBs from Sahebganj to Madhubani in connection with construction of Hajipur-Sagauli new BG rail line project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by GVV Constructions Private Limited-Bhubaneswar. The tendered cost of the work is ₹78.61 Cr, and it is currently In Progress with physical progress recorded at 34%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 78.61 after 1st variation value 110.59

?

Frequently Asked Questions

QWhat is the current status of the railway work "Balance earthwork, Blanketing work in embankment and construction of minor bridg"?
Status: In Progress. This East Central Railway work is being executed by GVV Constructions Private Limited-Bhubaneswar. Physical progress stands at 34%. Current date of completion (DOC): 31-12-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is GVV Constructions Private Limited-Bhubaneswar, Plot No 358 Saheed Nagar, Bhubaneswar, Odisha-751007, India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-02-24-25 / 00910690103878 dt 27.05.24. Work started on 27-05-2024.
QWhat is the cost of this railway work?
The tendered cost of "Balance earthwork, Blanketing work in embankment and constru" is ₹78.61 Cr (against an estimate of ₹89.48 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Balance earthwork, Blanketing work in embankment and constru" is one of hundreds of railway works covered.