East Central RailwayOverdue

Balance Earth work in filling in embankment, approach road and constrution of Minor Bridges, Road Under Bridge (RUBs), Height gauge & other miscellaneous work between Deoria (Excl.) to Sahebganj (Excl) in connection with Hajipur-Sugauli New BG Rail Line.

Work #99
As of March 2026

Estimate Cost

₹68.93 Cr

Sanctioned estimate

Tendered Cost

₹69.58 Cr

+0.9% vs estimate

Physical Progress

87%

Work completed

Status

Overdue

Current stage

East Central Railway — CAO (Con)Overdue
Tendered₹69.58 Cr
Progress87%
Started12-05-2022
Target DOC31-03-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
99
Agency
BRBA infratech LLP Alipurduar
Old Station Road, Alipurduar-736121
Acceptance / LOA
ECR/CAO/Con/WT/Agt/197 dt 04.07.22
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹68.93 Cr
Tendered Cost
₹69.58 Cr
Physical Progress
87%
Date Started
12-05-2022
Original DOC
11-04-2023
Extended DOC
31-03-2026

Balance Earth work in filling in embankment, approach road and constrution of Minor Bridges, Road Under Bridge (RUBs), Height gauge & other miscellaneous work between Deoria (Excl.) to Sahebganj (Excl) in connection with Hajipur-Sugauli New BG Rail Line. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s BRBA infratech LLP Alipurduar. The tendered cost of the work is ₹69.58 Cr, and it is currently Overdue with physical progress recorded at 87%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Balance Earth work in filling in embankment, approach road and constrution of Mi"?
Status: Overdue. This East Central Railway work is being executed by M/s BRBA infratech LLP Alipurduar. Physical progress stands at 87%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s BRBA infratech LLP Alipurduar, Old Station Road, Alipurduar-736121. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt/197 dt 04.07.22. Work started on 12-05-2022.
QWhat is the cost of this railway work?
The tendered cost of "Balance Earth work in filling in embankment, approach road a" is ₹69.58 Cr (against an estimate of ₹68.93 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Balance Earth work in filling in embankment, approach road a" is one of hundreds of railway works covered.