(Re-Tender) REMAINING WORK OF PLUG & PLAY PRE FABRICATED SHED AT PURNEA. ( PHASE-1 & PHASE-2)
Tender Amount
₹5.43 Cr
Awarded Cost
₹5.05 Cr
Start Date
—
Completion
—
(Re-Tender) REMAINING WORK OF PLUG & PLAY PRE FABRICATED SHED AT PURNEA. ( PHASE-1 & PHASE-2) is a infrastructure project in Purnia district, executed under Infrastructure Development Authority. The awarded cost of the project is ₹5.05 Cr, and the project is currently Ongoing.
This project is one of several infrastructure initiatives tracked across Purnia district as part of Bihar's broader development agenda. Related projects in the same district are listed below for comparison.
Project Details
Financial & Timeline
Executing Contractor
Ragini Enterprises →Tender & Bid Details
Contract & Vendor Details
Project Overview
(Re-Tender) REMAINING WORK OF PLUG & PLAY PRE FABRICATED SHED AT PURNEA. ( PHASE-1 & PHASE-2) is a infrastructure project in Purnia district, Bihar, being implemented by Infrastructure Development Authority. The project has an approved cost of ₹5.05 Cr. Current status is Ongoing.
Frequently Asked Questions
- QWhat is the current status of "(Re-Tender) REMAINING WORK OF PLUG & PLAY PRE FABRICATED SHED AT PURNEA. ( PHAS"?
- The current status of this project is "Ongoing". This is a infrastructure project in Purnia district, Bihar.
- QWhich department is responsible for this project?
- This project is being implemented by Infrastructure Development Authority, Government of Bihar. It falls under the Infrastructure category and is located in Purnia district.
- QWhat is the cost of this Bihar infrastructure project?
- The project cost is ₹5.05 Cr. This is a infrastructure project funded by the Government of Bihar under Infrastructure Development Authority.
- QWhat is the NIT number for this project's tender?
- The Notice Inviting Tender (NIT) number for this project is NIT- 41/TEN/IDA/24 Gr-04. The tender fee is ₹10,000. EMD amount: ₹10.87 L.
- QHas a contract or purchase order been issued for this project?
- Yes — Purchase Order No. 32394 (Contract PO) has been issued. Contract period: 2024-08-17 to 2024-08-24.