Construction of ROB and its approaches in between Dumraon and Baruna Railway Station in lieu of LC no. - 67/A in the district of Buxar, Bihar
Tender Amount
₹40.83 Cr
Awarded Cost
₹35.78 Cr
Start Date
—
Completion
—
Construction of ROB and its approaches in between Dumraon and Baruna Railway Station in lieu of LC no. - 67/A in the district of Buxar, Bihar is a road infra project in Buxar district, executed under Bihar State Road Development Corporation Limited. This work is part of the development of Buxar Bridge — government project titles use official department terminology rather than the common name. The awarded cost of the project is ₹35.78 Cr, and the project is currently Ongoing.
This project is one of several infrastructure initiatives tracked across Buxar district as part of Bihar's broader development agenda. Related projects in the same district are listed below for comparison.
Project Details
Financial & Timeline
Executing Contractor
Niraj Cement Structurals Ltd →Tender & Bid Details
Contract & Vendor Details
Vendor Company Registration (MCA)
Company registration data sourced from the Ministry of Corporate Affairs (data.gov.in), matched 2026-08-30 19:15:52.
Project Overview
Construction of ROB and its approaches in between Dumraon and Baruna Railway Station in lieu of LC no. - 67/A in the district of Buxar, Bihar is a road infra project in Buxar district, Bihar, being implemented by Bihar State Road Development Corporation Limited. The project has an approved cost of ₹35.78 Cr. Current status is Ongoing.
Frequently Asked Questions
- QWhat is the current status of "Construction of ROB and its approaches in between Dumraon and Baruna Railway Sta"?
- The current status of this project is "Ongoing". This is a road infra project in Buxar district, Bihar.
- QWhich department is responsible for this project?
- This project is being implemented by Bihar State Road Development Corporation Limited, Government of Bihar. It falls under the Road Infra category and is located in Buxar district.
- QWhat is the cost of this Bihar infrastructure project?
- The project cost is ₹35.78 Cr. This is a road infra project funded by the Government of Bihar under Bihar State Road Development Corporation Limited.
- QIs this the Buxar Bridge project?
- Yes — "Construction of ROB and its approaches in between Dumraon and Baruna Railway Station in lieu of LC no. - 67/A in the district of Buxar, Bihar" is the official government project title covering Buxar Bridge development works. Government project titles for this sector use official department terminology rather than the site's common name.
- QWhat is the NIT number for this project's tender?
- The Notice Inviting Tender (NIT) number for this project is BSRDC Ltd-3870/2022 - 2236 Dated-23.09.2024. The tender fee is ₹10,000. EMD amount: ₹50.84 L.
- QHas a contract or purchase order been issued for this project?
- Yes — Purchase Order No. 63517 (Contract PO) has been issued. Contract period: 2026-02-25 to 2026-03-14.