Construction of Goradih weir, Construction of Bhojpur weir, Construction of Habibpur weir, Construction of Dostani check dam, Construction of Babhagawan check dam & Construction of Usta check dam (Group 03)
Tender Amount
₹14.72 Cr
Awarded Cost
₹14.62 Cr
Start Date
—
Completion
—
Construction of Goradih weir, Construction of Bhojpur weir, Construction of Habibpur weir, Construction of Dostani check dam, Construction of Babhagawan check dam & Construction of Usta check dam (Group 03) is a water resources project in Bhojpur district, executed under Minor Water Resources Department. This work is part of the development of Bhojpur Irrigation Project — government project titles use official department terminology rather than the common name. The awarded cost of the project is ₹14.62 Cr, and the project is currently Ongoing.
This project is one of several infrastructure initiatives tracked across Bhojpur district as part of Bihar's broader development agenda. Related projects in the same district are listed below for comparison.
Project Details
Financial & Timeline
Executing Contractor
ARVIND kUMAR →Tender & Bid Details
Contract & Vendor Details
Project Overview
Construction of Goradih weir, Construction of Bhojpur weir, Construction of Habibpur weir, Construction of Dostani check dam, Construction of Babhagawan check dam & Construction of Usta check dam (Group 03) is a water resources project in Bhojpur district, Bihar, being implemented by Minor Water Resources Department. The project has an approved cost of ₹14.62 Cr. Current status is Ongoing.
Frequently Asked Questions
- QWhat is the current status of "Construction of Goradih weir, Construction of Bhojpur weir, Construction of Habi"?
- The current status of this project is "Ongoing". This is a water resources project in Bhojpur district, Bihar.
- QWhich department is responsible for this project?
- This project is being implemented by Minor Water Resources Department, Government of Bihar. It falls under the Water Resources category and is located in Bhojpur district.
- QWhat is the cost of this Bihar infrastructure project?
- The project cost is ₹14.62 Cr. This is a water resources project funded by the Government of Bihar under Minor Water Resources Department.
- QIs this the Bhojpur Irrigation Project project?
- Yes — "Construction of Goradih weir, Construction of Bhojpur weir, Construction of Habibpur weir, Construction of Dostani check dam, Construction of Babhagawan check dam & Construction of Usta check dam (Group 03)" is the official government project title covering Bhojpur Irrigation Project development works. Government project titles for this sector use official department terminology rather than the site's common name.
- QWhat is the NIT number for this project's tender?
- The Notice Inviting Tender (NIT) number for this project is 03/2024-25/MID/BHAGALPUR-GR-03. The tender fee is ₹10,000. EMD amount: ₹24.72 L.
- QHas a contract or purchase order been issued for this project?
- Yes — Purchase Order No. 44410 (Contract PO) has been issued. Contract period: 2025-04-02 to 2025-04-16.