Construction of Double Lane with Paved Shoulder of Islampur Bypass from Ch. 0+000 km to Ch. 7+700 km (Total length- 7.700 km) & construction of 3 nos. H.L. R.C.C. Bridge in Nalanda district under Road Division, Hilsa for the year 2024-25
Tender Amount
₹47.89 Cr
Awarded Cost
₹36.53 Cr
Start Date
—
Completion
—
Construction of Double Lane with Paved Shoulder of Islampur Bypass from Ch. 0+000 km to Ch. 7+700 km (Total length- 7.700 km) & construction of 3 nos. H.L. R.C.C. Bridge in Nalanda district under Road Division, Hilsa for the year 2024-25 is a transport project in Nalanda district, executed under Road Construction Department. This work is part of the development of Nalanda Highway — government project titles use official department terminology rather than the common name. The awarded cost of the project is ₹36.53 Cr, and the project is currently Ongoing.
This project is one of several infrastructure initiatives tracked across Nalanda district as part of Bihar's broader development agenda. Related projects in the same district are listed below for comparison.
Project Details
Financial & Timeline
Executing Contractor
M/s VINAY CONSTRUCTION →Tender & Bid Details
Contract & Vendor Details
Project Overview
Construction of Double Lane with Paved Shoulder of Islampur Bypass from Ch. 0+000 km to Ch. 7+700 km (Total length- 7.700 km) & construction of 3 nos. H.L. R.C.C. Bridge in Nalanda district under Road Division, Hilsa for the year 2024-25 is a transport project in Nalanda district, Bihar, being implemented by Road Construction Department. The project has an approved cost of ₹36.53 Cr. Current status is Ongoing.
Frequently Asked Questions
- QWhat is the current status of "Construction of Double Lane with Paved Shoulder of Islampur Bypass from Ch. 0+0"?
- The current status of this project is "Ongoing". This is a transport project in Nalanda district, Bihar.
- QWhich department is responsible for this project?
- This project is being implemented by Road Construction Department, Government of Bihar. It falls under the Transport category and is located in Nalanda district.
- QWhat is the cost of this Bihar infrastructure project?
- The project cost is ₹36.53 Cr. This is a transport project funded by the Government of Bihar under Road Construction Department.
- QIs this the Nalanda Highway project?
- Yes — "Construction of Double Lane with Paved Shoulder of Islampur Bypass from Ch. 0+000 km to Ch. 7+700 km (Total length- 7.700 km) & construction of 3 nos. H.L. R.C.C. Bridge in Nalanda district under Road Division, Hilsa for the year 2024-25" is the official government project title covering Nalanda Highway development works. Government project titles for this sector use official department terminology rather than the site's common name.
- QWhat is the NIT number for this project's tender?
- The Notice Inviting Tender (NIT) number for this project is NIT No.- RCD/Road/Hilsa/04/2024-25. The tender fee is ₹10,000. EMD amount: ₹57.89 L.
- QHas a contract or purchase order been issued for this project?
- Yes — Purchase Order No. 36590 (Contract PO) has been issued. Contract period: 2024-12-07 to 2024-12-17.