Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Bihar Infrastructure ProjectOngoing
Road Infra

Cons. of2 Lane with paved Shoulder of Selected Rd. stretches from Bakaur to Parsarma Sec-1( 13.300 to 18.875)NH-527A Parsarma to Bariyahi Sec-2(0 to 24.068)NH-327E Bangaon Bypass Sec-3(0 to 3.820)Mahishi Spur Rd. Sec-4(0 to 5.720)BMP Ph-I in Bihar

Tender Amount

₹484.54 Cr

Awarded Cost

₹551.51 Cr

Start Date

2023-12-15

Completion

2025-12-14

Cons. of2 Lane with paved Shoulder of Selected Rd. stretches from Bakaur to Parsarma Sec-1( 13.300 to 18.875)NH-527A Parsarma to Bariyahi Sec-2(0 to 24.068)NH-327E Bangaon Bypass Sec-3(0 to 3.820)Mahishi Spur Rd. Sec-4(0 to 5.720)BMP Ph-I in Bihar is a road infra project in Saharsa district, executed under NHAI. This work is part of the development of Saharsa Highway — government project titles use official department terminology rather than the common name. The awarded cost of the project is ₹551.51 Cr, and the project is currently Ongoing.

This project is one of several infrastructure initiatives tracked across Saharsa district as part of Bihar's broader development agenda. Related projects in the same district are listed below for comparison.

Project Details

DistrictSaharsa
DepartmentNHAI
CategoryRoad Infra
StatusOngoing
ContractorDhariwal Buildtech Limited

Financial & Timeline

Tender Amount₹484.54 Cr
Awarded Cost₹551.51 Cr
Start Date2023-12-15
End Date2025-12-14
Last Updated2023-12-15

Executing Contractor

Dhariwal Buildtech Limited

Project Overview

Cons. of2 Lane with paved Shoulder of Selected Rd. stretches from Bakaur to Parsarma Sec-1( 13.300 to 18.875)NH-527A Parsarma to Bariyahi Sec-2(0 to 24.068)NH-327E Bangaon Bypass Sec-3(0 to 3.820)Mahishi Spur Rd. Sec-4(0 to 5.720)BMP Ph-I in Bihar is a road infra project in Saharsa district, Bihar, being implemented by NHAI. The project has an approved cost of ₹551.51 Cr. Current status is Ongoing. Work commenced on 2023-12-15. Expected completion: 2025-12-14.

?

Frequently Asked Questions

QWhat is the current status of "Cons. of2 Lane with paved Shoulder of Selected Rd. stretches from Bakaur to Pars"?
The current status of this project is "Ongoing". Expected completion: 2025-12-14. This is a road infra project in Saharsa district, Bihar.
QWhich department is responsible for this project?
This project is being implemented by NHAI, Government of Bihar. It falls under the Road Infra category and is located in Saharsa district.
QWhat is the cost of this Bihar infrastructure project?
The project cost is ₹551.51 Cr. This is a road infra project funded by the Government of Bihar under NHAI.
QIs this the Saharsa Highway project?
Yes — "Cons. of2 Lane with paved Shoulder of Selected Rd. stretches from Bakaur to Parsarma Sec-1( 13.300 to 18.875)NH-527A Parsarma to Bariyahi Sec-2(0 to 24.068)NH-327E Bangaon Bypass Sec-3(0 to 3.820)Mahishi Spur Rd. Sec-4(0 to 5.720)BMP Ph-I in Bihar" is the official government project title covering Saharsa Highway development works. Government project titles for this sector use official department terminology rather than the site's common name.