Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)
Physical Progress
92.4%
Drone-monitored
Financial Progress
92.0%
Of awarded cost
Awarded Cost
₹1102 Cr
Contract value
Length
13.3 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
902
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
11-08-2023
Likely Date
31-03-2027
Completion
92.4%
Physical Done
Project Timeline
Awarded
12-02-2020
Construction Started
12-02-2020
In Progress
Near Completion
-
Completed
31-03-2027
Physical vs Financial Progress
Project Details
UPC
N/09072/01005/BR
National Highway
527 A
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
13.3 km
Contractor
Gammon Engineers & Contractors Pvt. Ltd. - Transrail Lighting Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
902 frames
Last Flight
2026-08-25
Cost & Timeline
Awarded Cost
₹1101.99 Cr
Capital Cost
₹1199.58 Cr
Start Date
12-02-2020
PCOD Date
-
Scheduled Completion
11-08-2023
Likely Completion
31-03-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 18:27:49
Contractor Profile
Gammon Engineers & Contractors Pvt. Ltd. - Transrail Lighting Ltd.
Project Intelligence
Construction is 92.4% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 13.3 km on 527 A, improving regional connectivity.
902 drone frames uploaded — real-time aerial monitoring is active for this project.
Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur) is a National Highways Authority of India (NHAI) project on 527 A in Bihar. The project has an awarded cost of ₹1101.99 Cr and is currently ongoing with physical progress at 92.4%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
902 frames · NHAI surveillance footage · UPC N/09072/01005/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)"?
- Current physical progress: 92.4%. Financial progress: 92.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 11-08-2023. Likely completion: 31-03-2027.
- QWho is the contractor for this NHAI highway project?
- The contractor for Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur) is Gammon Engineers & Contractors Pvt. Ltd. - Transrail Lighting Ltd.. The project is under RO-Patna and covers 13.3 km on 527 A.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹1101.99 Crore. Total capital cost: ₹1199.58 Crore. The project is on 527 A in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/09072/01005/BR in NHAI?
- UPC (Unique Project Code) N/09072/01005/BR refers to "Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)" — a National Highway project on 527 A in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.