Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)

UPC: N/09072/01005/BR

Physical Progress

92.4%

Drone-monitored

Financial Progress

92.0%

Of awarded cost

Awarded Cost

₹1102 Cr

Contract value

Length

13.3 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

902

Aerial captures

Project Progress

Physical Progress92.4%
Financial Progress92.0%

Stage

Under Construction (AD issued)

Due Date

11-08-2023

Likely Date

31-03-2027

Completion

92.4%

Physical Done

DoneRemaining

Project Timeline

Awarded

12-02-2020

Construction Started

12-02-2020

In Progress

Near Completion

-

Completed

31-03-2027

Physical vs Financial Progress

Project Details

UPC

N/09072/01005/BR

National Highway

527 A

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

13.3 km

Contractor

Gammon Engineers & Contractors Pvt. Ltd. - Transrail Lighting Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

902 frames

Last Flight

2026-08-25

Cost & Timeline

Awarded Cost

₹1101.99 Cr

Capital Cost

₹1199.58 Cr

Start Date

12-02-2020

PCOD Date

-

Scheduled Completion

11-08-2023

Likely Completion

31-03-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-13 18:27:49

Contractor Profile

Gammon Engineers & Contractors Pvt. Ltd. - Transrail Lighting Ltd.

RO-Patna527 AEPC

Project Intelligence

1

Construction is 92.4% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 13.3 km on 527 A, improving regional connectivity.

4

902 drone frames uploaded — real-time aerial monitoring is active for this project.

Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur) is a National Highways Authority of India (NHAI) project on 527 A in Bihar. The project has an awarded cost of ₹1101.99 Cr and is currently ongoing with physical progress at 92.4%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

902 frames · NHAI surveillance footage · UPC N/09072/01005/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)"?
Current physical progress: 92.4%. Financial progress: 92.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 11-08-2023. Likely completion: 31-03-2027.
QWho is the contractor for this NHAI highway project?
The contractor for Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur) is Gammon Engineers & Contractors Pvt. Ltd. - Transrail Lighting Ltd.. The project is under RO-Patna and covers 13.3 km on 527 A.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1101.99 Crore. Total capital cost: ₹1199.58 Crore. The project is on 527 A in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/09072/01005/BR in NHAI?
UPC (Unique Project Code) N/09072/01005/BR refers to "Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)" — a National Highway project on 527 A in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.