Umagaon - Saharsa Package - I (Combined) Umagaon-Kaluahi(0.000KM to 21.609Km) of NH227L;Saharghat-Rahika(0.000 Km to 26.130KM) of NH227J;Rahika-Rampatti (0.00 KM to 15.00KM) of NH527A;Bideshwarsthan-Bheja(0.000KM to 25.915KM) of NH527A.
Physical Progress
17.4%
Drone-monitored
Financial Progress
14.1%
Of awarded cost
Awarded Cost
₹1224 Cr
Contract value
Length
88.655 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
10426
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
01-07-2027
Likely Date
01-07-2027
Completion
17.4%
Physical Done
Project Timeline
Awarded
02-01-2025
Construction Started
02-01-2025
In Progress
Near Completion
-
Completed
01-07-2027
Physical vs Financial Progress
Project Details
UPC
N/09072/01007/BR
National Highway
227L
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
88.655 km
Contractor
Ram Kripal Singh Construction Pvt. Ltd
Project Stage
Under Construction (AD issued)
Drone Frames
10426 frames
Last Flight
2026-02-20
Cost & Timeline
Awarded Cost
₹1224.28 Cr
Capital Cost
₹1473.20 Cr
Start Date
02-01-2025
PCOD Date
-
Scheduled Completion
01-07-2027
Likely Completion
01-07-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 17:25:40
Contractor Profile
Ram Kripal Singh Construction Pvt. Ltd
Project Intelligence
Physical progress stands at 17.4%. Financial utilization at 14.1%.
Project is on schedule or ahead of planned completion date.
Covers 88.655 km on 227L, improving regional connectivity.
10426 drone frames uploaded — real-time aerial monitoring is active for this project.
Umagaon - Saharsa Package - I (Combined) Umagaon-Kaluahi(0.000KM to 21.609Km) of NH227L;Saharghat-Rahika(0.000 Km to 26.130KM) of NH227J;Rahika-Rampatti (0.00 KM to 15.00KM) of NH527A;Bideshwarsthan-Bheja(0.000KM to 25.915KM) of NH527A. is a National Highways Authority of India (NHAI) project on 227L in Bihar. The project has an awarded cost of ₹1224.28 Cr and is currently **ongoing** with physical progress at 17.4%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
10,426 frames · NHAI surveillance footage · UPC N/09072/01007/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Umagaon - Saharsa Package - I (Combined) Umagaon-Kaluahi(0.000KM to 21.609Km) of"?
- Current physical progress: 17.4%. Financial progress: 14.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 01-07-2027. Likely completion: 01-07-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for Umagaon - Saharsa Package - I (Combined) Umagaon-Kaluahi(0.000KM to 21.609Km) of NH227L;Saharghat-Rahika(0.000 Km to 26.130KM) of NH227J;Rahika-Rampatti (0.00 KM to 15.00KM) of NH527A;Bideshwarsthan-Bheja(0.000KM to 25.915KM) of NH527A. is Ram Kripal Singh Construction Pvt. Ltd. The project is under RO-Patna and covers 88.655 km on 227L.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1224.28 Crore. Total capital cost: ₹1473.20 Crore. The project is on 227L in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/09072/01007/BR in NHAI?
- UPC (Unique Project Code) N/09072/01007/BR refers to "Umagaon - Saharsa Package - I (Combined) Umagaon-Kaluahi(0.000KM to 21.609Km) of NH227L;Saharghat-Rahika(0.000 Km to 26.130KM) of NH227J;Rahika-Rampatti (0.00 KM to 15.00KM) of NH527A;Bideshwarsthan-Bheja(0.000KM to 25.915KM) of NH527A." — a National Highway project on 227L in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.