Physical Progress
17.4%
Drone-monitored
Financial Progress
14.1%
Of awarded cost
Awarded Cost
₹1224 Cr
Contract value
Length
88.655 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
10426
Aerial captures
Stage
Under Construction (AD issued)
Due Date
01-07-2027
Likely Date
01-07-2027
17.4%
Physical Done
Awarded
02-01-2025
Construction Started
02-01-2025
In Progress
Near Completion
-
Completed
01-07-2027
UPC
N/09072/01007/BR
National Highway
227L
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
88.655 km
Contractor
Ram Kripal Singh Construction Pvt. Ltd
Project Stage
Under Construction (AD issued)
Drone Frames
10426 frames
Last Flight
2026-02-20
Awarded Cost
₹1224.28 Cr
Capital Cost
₹1473.20 Cr
Start Date
02-01-2025
PCOD Date
-
Scheduled Completion
01-07-2027
Likely Completion
01-07-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 17:25:40
Ram Kripal Singh Construction Pvt. Ltd
Physical progress stands at 17.4%. Financial utilization at 14.1%.
Project is on schedule or ahead of planned completion date.
Covers 88.655 km on 227L, improving regional connectivity.
10426 drone frames uploaded — real-time aerial monitoring is active for this project.
10,426 frames · NHAI surveillance footage · UPC N/09072/01007/BR