Simaria (Km. 206.050) to Khagaria (Km. 266.282)
Physical Progress
97.7%
Drone-monitored
Financial Progress
96.8%
Of awarded cost
Awarded Cost
₹567 Cr
Contract value
Length
60.23 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
7007
Aerial captures
Project Progress
Stage
PCC Issued, CC Pending
Due Date
03-04-2019
Likely Date
31-12-2026
Completion
97.7%
Physical Done
Project Timeline
Awarded
05-10-2016
Construction Started
05-10-2016
In Progress
Near Completion
30-03-2023
Completed
31-12-2026
Physical vs Financial Progress
Project Details
UPC
N/08017/04001/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
60.23 km
Contractor
Punj Lloyd Infrastructue Ltd.
Project Stage
PCC Issued, CC Pending
Drone Frames
7007 frames
Last Flight
2026-07-27
Cost & Timeline
Awarded Cost
₹567.00 Cr
Capital Cost
₹664.02 Cr
Start Date
05-10-2016
PCOD Date
30-03-2023
Scheduled Completion
03-04-2019
Likely Completion
31-12-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-08-28 23:36:53
Contractor Profile
Punj Lloyd Infrastructue Ltd.
Project Intelligence
Construction is 97.7% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 60.23 km on 31, improving regional connectivity.
7007 drone frames uploaded — real-time aerial monitoring is active for this project.
Simaria (Km. 206.050) to Khagaria (Km. 266.282) is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹567.00 Cr and is currently ongoing with physical progress at 97.7%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
7,007 frames · NHAI surveillance footage · UPC N/08017/04001/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Simaria (Km. 206.050) to Khagaria (Km. 266.282)"?
- Current physical progress: 97.7%. Financial progress: 96.8%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 03-04-2019. Likely completion: 31-12-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for Simaria (Km. 206.050) to Khagaria (Km. 266.282) is Punj Lloyd Infrastructue Ltd.. The project is under RO-Patna and covers 60.23 km on 31.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹567.00 Crore. Total capital cost: ₹664.02 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08017/04001/BR in NHAI?
- UPC (Unique Project Code) N/08017/04001/BR refers to "Simaria (Km. 206.050) to Khagaria (Km. 266.282)" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.