Physical Progress
97.7%
Drone-monitored
Financial Progress
96.8%
Of awarded cost
Awarded Cost
₹567 Cr
Contract value
Length
60.23 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3309
Aerial captures
Stage
PCC Issued, CC Pending
Due Date
03-04-2019
Likely Date
31-10-2026
97.7%
Physical Done
Awarded
05-10-2016
Construction Started
05-10-2016
In Progress
Near Completion
30-03-2023
Completed
31-10-2026
UPC
N/08017/04001/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
60.23 km
Contractor
Punj Lloyd Infrastructue Ltd.
Project Stage
PCC Issued, CC Pending
Drone Frames
3309 frames
Last Flight
2026-01-27
Awarded Cost
₹567.00 Cr
Capital Cost
₹664.02 Cr
Start Date
05-10-2016
PCOD Date
30-03-2023
Scheduled Completion
03-04-2019
Likely Completion
31-10-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 16:08:04
Punj Lloyd Infrastructue Ltd.
Construction is 97.7% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 60.23 km on 31, improving regional connectivity.
3309 drone frames uploaded — real-time aerial monitoring is active for this project.
3,309 frames · NHAI surveillance footage · UPC N/08017/04001/BR