2nd Flyover (LCW) Parallel to Existing Flyover in Kishanganj Town
Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹153 Cr
Contract value
Length
3.18 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
365
Aerial captures
Project Progress
Stage
CC Issued
Due Date
28-06-2020
Likely Date
31-01-2025
Completion
100.0%
Physical Done
Project Timeline
Awarded
30-06-2018
Construction Started
30-06-2018
In Progress
Near Completion
18-08-2023
Completed
31-01-2025
Physical vs Financial Progress
Project Details
UPC
N/02023/03001/BR
National Highway
31
Regional Office
RO-Kolkata
State
Bihar
Mode
EPC
Length
3.18 km
Contractor
Bihar Rajya Pul Nirman Nigam Ltd.
Project Stage
CC Issued
Drone Frames
365 frames
Last Flight
2025-03-28
Cost & Timeline
Awarded Cost
₹152.70 Cr
Capital Cost
₹166.30 Cr
Start Date
30-06-2018
PCOD Date
18-08-2023
Scheduled Completion
28-06-2020
Likely Completion
31-01-2025
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 10:03:54
Contractor Profile
Bihar Rajya Pul Nirman Nigam Ltd.
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 3.18 km on 31, improving regional connectivity.
365 drone frames uploaded — real-time aerial monitoring is active for this project.
2nd Flyover (LCW) Parallel to Existing Flyover in Kishanganj Town is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹152.70 Cr and is currently 1 with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
365 frames · NHAI surveillance footage · UPC N/02023/03001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "2nd Flyover (LCW) Parallel to Existing Flyover in Kishanganj Town"?
- Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued. On schedule. Scheduled completion: 28-06-2020. Likely completion: 31-01-2025.
- Who is the contractor for this NHAI highway project?
- The contractor for 2nd Flyover (LCW) Parallel to Existing Flyover in Kishanganj Town is Bihar Rajya Pul Nirman Nigam Ltd.. The project is under RO-Kolkata and covers 3.18 km on 31.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹152.70 Crore. Total capital cost: ₹166.30 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/02023/03001/BR in NHAI?
- UPC (Unique Project Code) N/02023/03001/BR refers to "2nd Flyover (LCW) Parallel to Existing Flyover in Kishanganj Town" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.