Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900)
Physical Progress
100.0%
Drone-monitored
Financial Progress
99.0%
Of awarded cost
Awarded Cost
₹879 Cr
Contract value
Length
44.6 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2377
Aerial captures
Project Progress
Stage
PCC Issued, CC Pending
Due Date
10-12-2019
Likely Date
30-06-2026
Completion
100.0%
Physical Done
Project Timeline
Awarded
14-06-2017
Construction Started
14-06-2017
In Progress
Near Completion
01-10-2025
Completed
30-06-2026
Physical vs Financial Progress
Project Details
UPC
N/08017/02001/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
44.6 km
Contractor
BSCPL Infrastructure Ltd.
Project Stage
PCC Issued, CC Pending
Drone Frames
2377 frames
Last Flight
2026-02-20
Cost & Timeline
Awarded Cost
₹878.94 Cr
Capital Cost
₹1182.94 Cr
Start Date
14-06-2017
PCOD Date
01-10-2025
Scheduled Completion
10-12-2019
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 14:04:28
Contractor Profile
BSCPL Infrastructure Ltd.
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 44.6 km on 31, improving regional connectivity.
2377 drone frames uploaded — real-time aerial monitoring is active for this project.
Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900) is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹878.94 Cr and is currently ongoing with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,377 frames · NHAI surveillance footage · UPC N/08017/02001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900)"?
- Current physical progress: 100.0%. Financial progress: 99.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 10-12-2019. Likely completion: 30-06-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900) is BSCPL Infrastructure Ltd.. The project is under RO-Patna and covers 44.6 km on 31.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹878.94 Crore. Total capital cost: ₹1182.94 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08017/02001/BR in NHAI?
- UPC (Unique Project Code) N/08017/02001/BR refers to "Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900)" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.