Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
All NHAI Projects
31EPC 2377 Drone Frames

Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900)

UPC: N/08017/02001/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

99.0%

Of awarded cost

Awarded Cost

₹879 Cr

Contract value

Length

44.6 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

2377

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress99.0%

Stage

PCC Issued, CC Pending

Due Date

10-12-2019

Likely Date

30-06-2026

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

14-06-2017

Construction Started

14-06-2017

In Progress

Near Completion

01-10-2025

Completed

30-06-2026

Physical vs Financial Progress

Project Details

UPC

N/08017/02001/BR

National Highway

31

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

44.6 km

Contractor

BSCPL Infrastructure Ltd.

Project Stage

PCC Issued, CC Pending

Drone Frames

2377 frames

Last Flight

2026-02-20

Cost & Timeline

Awarded Cost

₹878.94 Cr

Capital Cost

₹1182.94 Cr

Start Date

14-06-2017

PCOD Date

01-10-2025

Scheduled Completion

10-12-2019

Likely Completion

30-06-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-18 14:04:28

Contractor Profile

BSCPL Infrastructure Ltd.

RO-Patna31EPC

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 44.6 km on 31, improving regional connectivity.

4

2377 drone frames uploaded — real-time aerial monitoring is active for this project.

Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900) is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹878.94 Cr and is currently ongoing with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

2,377 frames · NHAI surveillance footage · UPC N/08017/02001/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900)"?
Current physical progress: 100.0%. Financial progress: 99.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 10-12-2019. Likely completion: 30-06-2026.
Who is the contractor for this NHAI highway project?
The contractor for Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900) is BSCPL Infrastructure Ltd.. The project is under RO-Patna and covers 44.6 km on 31.
What is the cost of this NHAI highway project?
The awarded cost is ₹878.94 Crore. Total capital cost: ₹1182.94 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/08017/02001/BR in NHAI?
UPC (Unique Project Code) N/08017/02001/BR refers to "Bakhtiyarpur (Km 153.300) to Mokama (Km 197.900)" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.