Physical Progress
100.0%
Drone-monitored
Financial Progress
99.0%
Of awarded cost
Awarded Cost
₹879 Cr
Contract value
Length
44.6 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2377
Aerial captures
Stage
PCC Issued, CC Pending
Due Date
10-12-2019
Likely Date
30-06-2026
100.0%
Physical Done
Awarded
14-06-2017
Construction Started
14-06-2017
In Progress
Near Completion
01-10-2025
Completed
30-06-2026
UPC
N/08017/02001/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
44.6 km
Contractor
BSCPL Infrastructure Ltd.
Project Stage
PCC Issued, CC Pending
Drone Frames
2377 frames
Last Flight
2026-02-20
Awarded Cost
₹878.94 Cr
Capital Cost
₹1182.94 Cr
Start Date
14-06-2017
PCOD Date
01-10-2025
Scheduled Completion
10-12-2019
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 14:04:28
BSCPL Infrastructure Ltd.
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 44.6 km on 31, improving regional connectivity.
2377 drone frames uploaded — real-time aerial monitoring is active for this project.
2,377 frames · NHAI surveillance footage · UPC N/08017/02001/BR