Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹1161 Cr
Contract value
Length
8.15 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1020
Aerial captures
Stage
CC Issued & O&M by Construction Agency
Due Date
07-02-2022
Likely Date
30-04-2026
100.0%
Physical Done
Awarded
11-08-2018
Construction Started
11-08-2018
In Progress
Near Completion
-
Completed
30-04-2026
UPC
N/08017/03001/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
8.15 km
Contractor
Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.
Project Stage
CC Issued & O&M by Construction Agency
Drone Frames
1020 frames
Last Flight
2025-10-28
Awarded Cost
₹1161.00 Cr
Capital Cost
₹1309.47 Cr
Start Date
11-08-2018
PCOD Date
-
Scheduled Completion
07-02-2022
Likely Completion
30-04-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 15:55:49
Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 8.15 km on 31, improving regional connectivity.
1020 drone frames uploaded — real-time aerial monitoring is active for this project.
1,020 frames · NHAI surveillance footage · UPC N/08017/03001/BR