All NHAI Projects
31HAM 1152 Drone Frames

Aunta - Simaria including Ganga Bridge

UPC: N/08017/03001/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

100.0%

Of awarded cost

Awarded Cost

₹1161 Cr

Contract value

Length

8.15 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

1152

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress100.0%

Stage

CC Issued & O&M by Construction Agency

Due Date

07-02-2022

Likely Date

30-04-2026

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

11-08-2018

Construction Started

11-08-2018

In Progress

Near Completion

-

Completed

30-04-2026

Physical vs Financial Progress

Project Details

UPC

N/08017/03001/BR

National Highway

31

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

8.15 km

Contractor

Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.

Project Stage

CC Issued & O&M by Construction Agency

Drone Frames

1152 frames

Last Flight

2026-04-22

Cost & Timeline

Awarded Cost

₹1161.00 Cr

Capital Cost

₹1309.47 Cr

Start Date

11-08-2018

PCOD Date

-

Scheduled Completion

07-02-2022

Likely Completion

30-04-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-03 12:09:25

Contractor Profile

Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.

RO-Patna31HAM

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 8.15 km on 31, improving regional connectivity.

4

1152 drone frames uploaded — real-time aerial monitoring is active for this project.

Aunta - Simaria including Ganga Bridge is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹1161.00 Cr and is currently 1 with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

1,152 frames · NHAI surveillance footage · UPC N/08017/03001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Aunta - Simaria including Ganga Bridge"?
Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued & O&M by Construction Agency. On schedule. Scheduled completion: 07-02-2022. Likely completion: 30-04-2026.
QWho is the contractor for this NHAI highway project?
The contractor for Aunta - Simaria including Ganga Bridge is Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.. The project is under RO-Patna and covers 8.15 km on 31.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1161.00 Crore. Total capital cost: ₹1309.47 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08017/03001/BR in NHAI?
UPC (Unique Project Code) N/08017/03001/BR refers to "Aunta - Simaria including Ganga Bridge" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.