Aunta - Simaria including Ganga Bridge
Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹1161 Cr
Contract value
Length
8.15 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1152
Aerial captures
Project Progress
Stage
CC Issued & O&M by Construction Agency
Due Date
07-02-2022
Likely Date
30-04-2026
Completion
100.0%
Physical Done
Project Timeline
Awarded
11-08-2018
Construction Started
11-08-2018
In Progress
Near Completion
-
Completed
30-04-2026
Physical vs Financial Progress
Project Details
UPC
N/08017/03001/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
8.15 km
Contractor
Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.
Project Stage
CC Issued & O&M by Construction Agency
Drone Frames
1152 frames
Last Flight
2026-04-22
Cost & Timeline
Awarded Cost
₹1161.00 Cr
Capital Cost
₹1309.47 Cr
Start Date
11-08-2018
PCOD Date
-
Scheduled Completion
07-02-2022
Likely Completion
30-04-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-08-03 12:09:25
Contractor Profile
Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 8.15 km on 31, improving regional connectivity.
1152 drone frames uploaded — real-time aerial monitoring is active for this project.
Aunta - Simaria including Ganga Bridge is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹1161.00 Cr and is currently 1 with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
1,152 frames · NHAI surveillance footage · UPC N/08017/03001/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Aunta - Simaria including Ganga Bridge"?
- Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued & O&M by Construction Agency. On schedule. Scheduled completion: 07-02-2022. Likely completion: 30-04-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for Aunta - Simaria including Ganga Bridge is Welspun Enterprises Ltd. In consortium with Welspun Energy P. Ltd.. The project is under RO-Patna and covers 8.15 km on 31.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹1161.00 Crore. Total capital cost: ₹1309.47 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08017/03001/BR in NHAI?
- UPC (Unique Project Code) N/08017/03001/BR refers to "Aunta - Simaria including Ganga Bridge" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.