Routine Maintenance and Incident Management services Engagement of Crane, Ambulance & Patrolling Vehicle for accident and Traffic Management System at Bhagalpur Bypass Toll plaza located at km. 137.275 in the section of Lodipur Kala and Jichho village (Km. 124.175 to Km. 140.850) on NH- 80 Section in the State of Bihar.
Physical Progress
0.0%
Drone-monitored
Financial Progress
0.0%
Of awarded cost
Awarded Cost
₹1 Cr
Contract value
Length
16.675 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
N/A
Aerial captures
Project Progress
Stage
Under O&M through OMT/TOT/O&M Agency at Site
Due Date
03-09-2026
Likely Date
-
Completion
0.0%
Physical Done
Project Timeline
Awarded
03-09-2024
Construction Started
03-09-2024
In Progress
Near Completion
-
Completed
-
Physical vs Financial Progress
Project Details
UPC
N/17001/01130/BR
National Highway
NH-80
Regional Office
RO-Patna
State
Bihar
Mode
Not Applicable
Length
16.675 km
Contractor
K L Enterprises
Project Stage
Under O&M through OMT/TOT/O&M Agency at Site
Drone Frames
N/A
Last Flight
N/A
Cost & Timeline
Awarded Cost
₹0.69 Cr
Capital Cost
N/A
Start Date
03-09-2024
PCOD Date
-
Scheduled Completion
03-09-2026
Likely Completion
-
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-20 21:44:13
Contractor Profile
K L Enterprises
Project Intelligence
Physical progress stands at 0.0%. Financial utilization at 0.0%.
Project is on schedule or ahead of planned completion date.
Covers 16.675 km on NH-80, improving regional connectivity.
Routine Maintenance and Incident Management services Engagement of Crane, Ambulance & Patrolling Vehicle for accident and Traffic Management System at Bhagalpur Bypass Toll plaza located at km. 137.275 in the section of Lodipur Kala and Jichho village (Km. 124.175 to Km. 140.850) on NH- 80 Section in the State of Bihar. is a National Highways Authority of India (NHAI) project on NH-80 in Bihar. The project has an awarded cost of ₹0.69 Cr and is currently ongoing with physical progress at 0.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Routine Maintenance and Incident Management services Engagement of Crane, Ambula"?
- Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Under O&M through OMT/TOT/O&M Agency at Site. On schedule. Scheduled completion: 03-09-2026. Likely completion: -.
- QWho is the contractor for this NHAI highway project?
- The contractor for Routine Maintenance and Incident Management services Engagement of Crane, Ambulance & Patrolling Vehicle for accident and Traffic Management System at Bhagalpur Bypass Toll plaza located at km. 137.275 in the section of Lodipur Kala and Jichho village (Km. 124.175 to Km. 140.850) on NH- 80 Section in the State of Bihar. is K L Enterprises. The project is under RO-Patna and covers 16.675 km on NH-80.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹0.69 Crore. The project is on NH-80 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/17001/01130/BR in NHAI?
- UPC (Unique Project Code) N/17001/01130/BR refers to "Routine Maintenance and Incident Management services Engagement of Crane, Ambulance & Patrolling Vehicle for accident and Traffic Management System at Bhagalpur Bypass Toll plaza located at km. 137.275 in the section of Lodipur Kala and Jichho village (Km. 124.175 to Km. 140.850) on NH- 80 Section in the State of Bihar." — a National Highway project on NH-80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.