All NHAI Projects
NH-22,NH-22EPC

Construction of Flyovers at (i) Major Junction between NH-77 & SH-49 (Y- Junction) at Mahua Chowk & (ii) Intersection between NH-77 & MDR (Lalganj to Muzaffarpur) (Y-Junction) at Fakuli in four-laning of Hazipur & Muzaffarpur Section of Nh -22

UPC: N/05014/01004/BR

Physical Progress

0.0%

Drone-monitored

Financial Progress

0.0%

Of awarded cost

Awarded Cost

₹70 Cr

Contract value

Length

2.51 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

N/A

Aerial captures

Project Progress

Physical Progress0.0%
Financial Progress0.0%

Stage

Awarded, Not Appointed

Due Date

-

Likely Date

-

Completion

0.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

Appointed Date Pending

Construction Started

Appointed Date Pending

In Progress

Near Completion

-

Completed

-

Physical vs Financial Progress

Project Details

UPC

N/05014/01004/BR

National Highway

NH-22,NH-22

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

2.51 km

Contractor

JSP Project Pvt Ltd.

Project Stage

Awarded, Not Appointed

Drone Frames

N/A

Last Flight

N/A

Cost & Timeline

Awarded Cost

₹69.90 Cr

Capital Cost

N/A

Start Date

Appointed Date Pending

PCOD Date

-

Scheduled Completion

-

Likely Completion

-

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:44:42

Contractor Profile

JSP Project Pvt Ltd.

RO-PatnaNH-22,NH-22EPC

Project Intelligence

1

Physical progress stands at 0.0%. Financial utilization at 0.0%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 2.51 km on NH-22,NH-22, improving regional connectivity.

Construction of Flyovers at (i) Major Junction between NH-77 & SH-49 (Y- Junction) at Mahua Chowk & (ii) Intersection between NH-77 & MDR (Lalganj to Muzaffarpur) (Y-Junction) at Fakuli in four-laning of Hazipur & Muzaffarpur Section of Nh -22 is a National Highways Authority of India (NHAI) project on NH-22,NH-22 in Bihar. The project has an awarded cost of ₹69.90 Cr and is currently ongoing with physical progress at 0.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Construction of Flyovers at (i) Major Junction between NH-77 & SH-49 (Y- Junctio"?
Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Awarded, Not Appointed. On schedule. Scheduled completion: -. Likely completion: -.
QWho is the contractor for this NHAI highway project?
The contractor for Construction of Flyovers at (i) Major Junction between NH-77 & SH-49 (Y- Junction) at Mahua Chowk & (ii) Intersection between NH-77 & MDR (Lalganj to Muzaffarpur) (Y-Junction) at Fakuli in four-laning of Hazipur & Muzaffarpur Section of Nh -22 is JSP Project Pvt Ltd.. The project is under RO-Patna and covers 2.51 km on NH-22,NH-22.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹69.90 Crore. The project is on NH-22,NH-22 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/05014/01004/BR in NHAI?
UPC (Unique Project Code) N/05014/01004/BR refers to "Construction of Flyovers at (i) Major Junction between NH-77 & SH-49 (Y- Junction) at Mahua Chowk & (ii) Intersection between NH-77 & MDR (Lalganj to Muzaffarpur) (Y-Junction) at Fakuli in four-laning of Hazipur & Muzaffarpur Section of Nh -22" — a National Highway project on NH-22,NH-22 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.