Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode
Physical Progress
10.6%
Drone-monitored
Financial Progress
9.5%
Of awarded cost
Awarded Cost
₹41 Cr
Contract value
Length
1.4 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
N/A
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
28-11-2026
Likely Date
28-11-2026
Completion
10.6%
Physical Done
Project Timeline
Awarded
29-04-2026
Construction Started
29-04-2026
In Progress
Near Completion
-
Completed
28-11-2026
Physical vs Financial Progress
Project Details
UPC
N/08055/02008/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
1.4 km
Contractor
RKEC Projects Limited
Project Stage
Under Construction (AD issued)
Drone Frames
N/A
Last Flight
N/A
Cost & Timeline
Awarded Cost
₹40.50 Cr
Capital Cost
₹34.41 Cr
Start Date
29-04-2026
PCOD Date
-
Scheduled Completion
28-11-2026
Likely Completion
28-11-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-20 21:40:39
Contractor Profile
RKEC Projects Limited
Project Intelligence
Physical progress stands at 10.6%. Financial utilization at 9.5%.
Project is on schedule or ahead of planned completion date.
Covers 1.4 km on 31, improving regional connectivity.
Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹40.50 Cr and is currently ongoing with physical progress at 10.6%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Balance work of new bridge on Gandak river including approaches and rehabilitati"?
- Current physical progress: 10.6%. Financial progress: 9.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 28-11-2026. Likely completion: 28-11-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode is RKEC Projects Limited. The project is under RO-Patna and covers 1.4 km on 31.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹40.50 Crore. Total capital cost: ₹34.41 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08055/02008/BR in NHAI?
- UPC (Unique Project Code) N/08055/02008/BR refers to "Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.