All NHAI Projects
31EPC

Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode

UPC: N/08055/02008/BR

Physical Progress

10.6%

Drone-monitored

Financial Progress

9.5%

Of awarded cost

Awarded Cost

₹41 Cr

Contract value

Length

1.4 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

N/A

Aerial captures

Project Progress

Physical Progress10.6%
Financial Progress9.5%

Stage

Under Construction (AD issued)

Due Date

28-11-2026

Likely Date

28-11-2026

Completion

10.6%

Physical Done

DoneRemaining

Project Timeline

Awarded

29-04-2026

Construction Started

29-04-2026

In Progress

Near Completion

-

Completed

28-11-2026

Physical vs Financial Progress

Project Details

UPC

N/08055/02008/BR

National Highway

31

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

1.4 km

Contractor

RKEC Projects Limited

Project Stage

Under Construction (AD issued)

Drone Frames

N/A

Last Flight

N/A

Cost & Timeline

Awarded Cost

₹40.50 Cr

Capital Cost

₹34.41 Cr

Start Date

29-04-2026

PCOD Date

-

Scheduled Completion

28-11-2026

Likely Completion

28-11-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:40:39

Contractor Profile

RKEC Projects Limited

RO-Patna31EPC

Project Intelligence

1

Physical progress stands at 10.6%. Financial utilization at 9.5%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 1.4 km on 31, improving regional connectivity.

Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹40.50 Cr and is currently ongoing with physical progress at 10.6%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Balance work of new bridge on Gandak river including approaches and rehabilitati"?
Current physical progress: 10.6%. Financial progress: 9.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 28-11-2026. Likely completion: 28-11-2026.
QWho is the contractor for this NHAI highway project?
The contractor for Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode is RKEC Projects Limited. The project is under RO-Patna and covers 1.4 km on 31.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹40.50 Crore. Total capital cost: ₹34.41 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08055/02008/BR in NHAI?
UPC (Unique Project Code) N/08055/02008/BR refers to "Balance work of new bridge on Gandak river including approaches and rehabilitation of the existing Gandak Bridge at Km 206+436 and Mahi Bridge at Km 183+209 of Chhapra-Hajipur Section of NH-19 (New NH-31) in the state of Bihar on EPC mode" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.