Physical Progress
10.1%
Drone-monitored
Financial Progress
10.0%
Of awarded cost
Awarded Cost
₹1399 Cr
Contract value
Length
50.12 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4262
Aerial captures
Stage
Under Construction (AD issued)
Due Date
19-11-2026
Likely Date
19-11-2028
10.1%
Physical Done
Awarded
20-11-2024
Construction Started
20-11-2024
In Progress
Near Completion
-
Completed
19-11-2028
UPC
N/08079/01002/BR
National Highway
227A
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
50.12 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4262 frames
Last Flight
2026-02-24
Awarded Cost
₹1399.22 Cr
Capital Cost
₹1431.36 Cr
Start Date
20-11-2024
PCOD Date
-
Scheduled Completion
19-11-2026
Likely Completion
19-11-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 15:37:28
Megha Engineering and Infrastructure Ltd.
Physical progress stands at 10.1%. Financial utilization at 10.0%.
Project is on schedule or ahead of planned completion date.
Covers 50.12 km on 227A, improving regional connectivity.
4262 drone frames uploaded — real-time aerial monitoring is active for this project.
4,262 frames · NHAI surveillance footage · UPC N/08079/01002/BR