4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A
Physical Progress
10.1%
Drone-monitored
Financial Progress
10.0%
Of awarded cost
Awarded Cost
₹1399 Cr
Contract value
Length
50.12 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4262
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
19-11-2026
Likely Date
19-11-2028
Completion
10.1%
Physical Done
Project Timeline
Awarded
20-11-2024
Construction Started
20-11-2024
In Progress
Near Completion
-
Completed
19-11-2028
Physical vs Financial Progress
Project Details
UPC
N/08079/01002/BR
National Highway
227A
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
50.12 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4262 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹1399.22 Cr
Capital Cost
₹1431.36 Cr
Start Date
20-11-2024
PCOD Date
-
Scheduled Completion
19-11-2026
Likely Completion
19-11-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 15:37:28
Contractor Profile
Megha Engineering and Infrastructure Ltd.
Project Intelligence
Physical progress stands at 10.1%. Financial utilization at 10.0%.
Project is on schedule or ahead of planned completion date.
Covers 50.12 km on 227A, improving regional connectivity.
4262 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A is a National Highways Authority of India (NHAI) project on 227A in Bihar. The project has an awarded cost of ₹1399.22 Cr and is currently ongoing with physical progress at 10.1%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,262 frames · NHAI surveillance footage · UPC N/08079/01002/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of "?
- Current physical progress: 10.1%. Financial progress: 10.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 19-11-2026. Likely completion: 19-11-2028.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 50.12 km on 227A.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1399.22 Crore. Total capital cost: ₹1431.36 Crore. The project is on 227A in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08079/01002/BR in NHAI?
- UPC (Unique Project Code) N/08079/01002/BR refers to "4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A" — a National Highway project on 227A in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.