Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
All NHAI Projects
227AHAM 4262 Drone Frames

4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A

UPC: N/08079/01002/BR

Physical Progress

10.1%

Drone-monitored

Financial Progress

10.0%

Of awarded cost

Awarded Cost

₹1399 Cr

Contract value

Length

50.12 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

4262

Aerial captures

Project Progress

Physical Progress10.1%
Financial Progress10.0%

Stage

Under Construction (AD issued)

Due Date

19-11-2026

Likely Date

19-11-2028

Completion

10.1%

Physical Done

DoneRemaining

Project Timeline

Awarded

20-11-2024

Construction Started

20-11-2024

In Progress

Near Completion

-

Completed

19-11-2028

Physical vs Financial Progress

Project Details

UPC

N/08079/01002/BR

National Highway

227A

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

50.12 km

Contractor

Megha Engineering and Infrastructure Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

4262 frames

Last Flight

2026-02-24

Cost & Timeline

Awarded Cost

₹1399.22 Cr

Capital Cost

₹1431.36 Cr

Start Date

20-11-2024

PCOD Date

-

Scheduled Completion

19-11-2026

Likely Completion

19-11-2028

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-16 15:37:28

Contractor Profile

Megha Engineering and Infrastructure Ltd.

RO-Patna227AHAM

Project Intelligence

1

Physical progress stands at 10.1%. Financial utilization at 10.0%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 50.12 km on 227A, improving regional connectivity.

4

4262 drone frames uploaded — real-time aerial monitoring is active for this project.

4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A is a National Highways Authority of India (NHAI) project on 227A in Bihar. The project has an awarded cost of ₹1399.22 Cr and is currently ongoing with physical progress at 10.1%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

4,262 frames · NHAI surveillance footage · UPC N/08079/01002/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of "?
Current physical progress: 10.1%. Financial progress: 10.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 19-11-2026. Likely completion: 19-11-2028.
Who is the contractor for this NHAI highway project?
The contractor for 4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 50.12 km on 227A.
What is the cost of this NHAI highway project?
The awarded cost is ₹1399.22 Crore. Total capital cost: ₹1431.36 Crore. The project is on 227A in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/08079/01002/BR in NHAI?
UPC (Unique Project Code) N/08079/01002/BR refers to "4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A" — a National Highway project on 227A in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.