4L Greenfield starting from NH-30 near Saristabad (Patna) to Nathupur (Project end point of Patna-Gaya-Dobhi Section of NH-83)

UPC: N/08068/01005/BR

Physical Progress

90.0%

Drone-monitored

Financial Progress

86.4%

Of awarded cost

Awarded Cost

₹97 Cr

Contract value

Length

3.914 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

206

Aerial captures

Project Progress

Physical Progress90.0%
Financial Progress86.4%

Stage

Under Construction (AD issued)

Due Date

27-08-2025

Likely Date

31-10-2026

Completion

90.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

08-03-2024

Construction Started

08-03-2024

In Progress

Near Completion

-

Completed

31-10-2026

Physical vs Financial Progress

Project Details

UPC

N/08068/01005/BR

National Highway

83

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

3.914 km

Contractor

H.S. Engineers & Associates-Velji Ratna Sorathia Infra Pvt. Ltd. JV

Project Stage

Under Construction (AD issued)

Drone Frames

206 frames

Last Flight

2025-10-27

Cost & Timeline

Awarded Cost

₹96.77 Cr

Capital Cost

₹488.24 Cr

Start Date

08-03-2024

PCOD Date

-

Scheduled Completion

27-08-2025

Likely Completion

31-10-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:41:30

Contractor Profile

H.S. Engineers & Associates-Velji Ratna Sorathia Infra Pvt. Ltd. JV

RO-Patna83EPC

Project Intelligence

1

Construction is 90.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 3.914 km on 83, improving regional connectivity.

4

206 drone frames uploaded — real-time aerial monitoring is active for this project.

4L Greenfield starting from NH-30 near Saristabad (Patna) to Nathupur (Project end point of Patna-Gaya-Dobhi Section of NH-83) is a National Highways Authority of India (NHAI) project on 83 in Bihar. The project has an awarded cost of ₹96.77 Cr and is currently ongoing with physical progress at 90.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

206 frames · NHAI surveillance footage · UPC N/08068/01005/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L Greenfield starting from NH-30 near Saristabad (Patna) to Nathupur (Project e"?
Current physical progress: 90.0%. Financial progress: 86.4%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 27-08-2025. Likely completion: 31-10-2026.
QWho is the contractor for this NHAI highway project?
The contractor for 4L Greenfield starting from NH-30 near Saristabad (Patna) to Nathupur (Project end point of Patna-Gaya-Dobhi Section of NH-83) is H.S. Engineers & Associates-Velji Ratna Sorathia Infra Pvt. Ltd. JV. The project is under RO-Patna and covers 3.914 km on 83.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹96.77 Crore. Total capital cost: ₹488.24 Crore. The project is on 83 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08068/01005/BR in NHAI?
UPC (Unique Project Code) N/08068/01005/BR refers to "4L Greenfield starting from NH-30 near Saristabad (Patna) to Nathupur (Project end point of Patna-Gaya-Dobhi Section of NH-83)" — a National Highway project on 83 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.