Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹273 Cr
Contract value
Length
9.26 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
924
Aerial captures
Stage
CC Issued
Due Date
17-04-2018
Likely Date
31-01-2025
100.0%
Physical Done
Awarded
18-04-2016
Construction Started
18-04-2016
In Progress
Near Completion
31-07-2023
Completed
31-01-2025
UPC
N/07015/01002/BR
National Highway
57A
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
9.26 km
Contractor
JKM Infra Projects Ltd.
Project Stage
CC Issued
Drone Frames
924 frames
Last Flight
2025-03-28
Awarded Cost
₹273.35 Cr
Capital Cost
₹352.09 Cr
Start Date
18-04-2016
PCOD Date
31-07-2023
Scheduled Completion
17-04-2018
Likely Completion
31-01-2025
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:11:53
JKM Infra Projects Ltd.
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 9.26 km on 57A, improving regional connectivity.
924 drone frames uploaded — real-time aerial monitoring is active for this project.
924 frames · NHAI surveillance footage · UPC N/07015/01002/BR