4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A

UPC: N/07015/01002/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

100.0%

Of awarded cost

Awarded Cost

₹273 Cr

Contract value

Length

9.26 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

924

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress100.0%

Stage

CC Issued

Due Date

17-04-2018

Likely Date

31-01-2025

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

18-04-2016

Construction Started

18-04-2016

In Progress

Near Completion

31-07-2023

Completed

31-01-2025

Physical vs Financial Progress

Project Details

UPC

N/07015/01002/BR

National Highway

57A

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

9.26 km

Contractor

JKM Infra Projects Ltd.

Project Stage

CC Issued

Drone Frames

924 frames

Last Flight

2025-03-28

Cost & Timeline

Awarded Cost

₹273.35 Cr

Capital Cost

₹352.09 Cr

Start Date

18-04-2016

PCOD Date

31-07-2023

Scheduled Completion

17-04-2018

Likely Completion

31-01-2025

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-18 13:11:53

Contractor Profile

JKM Infra Projects Ltd.

RO-Patna57AEPC

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 9.26 km on 57A, improving regional connectivity.

4

924 drone frames uploaded — real-time aerial monitoring is active for this project.

4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A is a National Highways Authority of India (NHAI) project on 57A in Bihar. The project has an awarded cost of ₹273.35 Cr and is currently 1 with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

924 frames · NHAI surveillance footage · UPC N/07015/01002/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani)"?
Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued. On schedule. Scheduled completion: 17-04-2018. Likely completion: 31-01-2025.
QWho is the contractor for this NHAI highway project?
The contractor for 4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A is JKM Infra Projects Ltd.. The project is under RO-Patna and covers 9.26 km on 57A.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹273.35 Crore. Total capital cost: ₹352.09 Crore. The project is on 57A in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/07015/01002/BR in NHAI?
UPC (Unique Project Code) N/07015/01002/BR refers to "4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A" — a National Highway project on 57A in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.