4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A
Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹273 Cr
Contract value
Length
9.26 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
924
Aerial captures
Project Progress
Stage
CC Issued
Due Date
17-04-2018
Likely Date
31-01-2025
Completion
100.0%
Physical Done
Project Timeline
Awarded
18-04-2016
Construction Started
18-04-2016
In Progress
Near Completion
31-07-2023
Completed
31-01-2025
Physical vs Financial Progress
Project Details
UPC
N/07015/01002/BR
National Highway
57A
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
9.26 km
Contractor
JKM Infra Projects Ltd.
Project Stage
CC Issued
Drone Frames
924 frames
Last Flight
2025-03-28
Cost & Timeline
Awarded Cost
₹273.35 Cr
Capital Cost
₹352.09 Cr
Start Date
18-04-2016
PCOD Date
31-07-2023
Scheduled Completion
17-04-2018
Likely Completion
31-01-2025
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:11:53
Contractor Profile
JKM Infra Projects Ltd.
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 9.26 km on 57A, improving regional connectivity.
924 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A is a National Highways Authority of India (NHAI) project on 57A in Bihar. The project has an awarded cost of ₹273.35 Cr and is currently 1 with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
924 frames · NHAI surveillance footage · UPC N/07015/01002/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani)"?
- Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued. On schedule. Scheduled completion: 17-04-2018. Likely completion: 31-01-2025.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A is JKM Infra Projects Ltd.. The project is under RO-Patna and covers 9.26 km on 57A.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹273.35 Crore. Total capital cost: ₹352.09 Crore. The project is on 57A in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/07015/01002/BR in NHAI?
- UPC (Unique Project Code) N/07015/01002/BR refers to "4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC at Jogbani) of NH-57A" — a National Highway project on 57A in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.