Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode
Physical Progress
22.3%
Drone-monitored
Financial Progress
14.6%
Of awarded cost
Awarded Cost
₹368 Cr
Contract value
Length
3.3 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
582
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
19-02-2028
Likely Date
19-02-2028
Completion
22.3%
Physical Done
Project Timeline
Awarded
20-08-2025
Construction Started
20-08-2025
In Progress
Near Completion
-
Completed
19-02-2028
Physical vs Financial Progress
Project Details
UPC
N/08034/03004/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
3.3 km
Contractor
ASC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
582 frames
Last Flight
2026-08-26
Cost & Timeline
Awarded Cost
₹368.00 Cr
Capital Cost
₹531.61 Cr
Start Date
20-08-2025
PCOD Date
-
Scheduled Completion
19-02-2028
Likely Completion
19-02-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 18:44:00
Contractor Profile
ASC Infratech Pvt. Ltd.
Project Intelligence
Physical progress stands at 22.3%. Financial utilization at 14.6%.
Project is on schedule or ahead of planned completion date.
Covers 3.3 km on 31, improving regional connectivity.
582 drone frames uploaded — real-time aerial monitoring is active for this project.
Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹368.00 Cr and is currently ongoing with physical progress at 22.3%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
582 frames · NHAI surveillance footage · UPC N/08034/03004/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Construction of additional 3-Lane Bridge over River Ganga for connection between"?
- Current physical progress: 22.3%. Financial progress: 14.6%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 19-02-2028. Likely completion: 19-02-2028.
- QWho is the contractor for this NHAI highway project?
- The contractor for Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode is ASC Infratech Pvt. Ltd.. The project is under RO-Patna and covers 3.3 km on 31.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹368.00 Crore. Total capital cost: ₹531.61 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08034/03004/BR in NHAI?
- UPC (Unique Project Code) N/08034/03004/BR refers to "Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.