Physical Progress
17.6%
Drone-monitored
Financial Progress
10.5%
Of awarded cost
Awarded Cost
₹368 Cr
Contract value
Length
3.3 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
234
Aerial captures
Stage
Under Construction (AD issued)
Due Date
19-02-2028
Likely Date
19-02-2028
17.6%
Physical Done
Awarded
20-08-2025
Construction Started
20-08-2025
In Progress
Near Completion
-
Completed
19-02-2028
UPC
N/08034/03004/BR
National Highway
31
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
3.3 km
Contractor
ASC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
234 frames
Last Flight
2026-03-23
Awarded Cost
₹368.00 Cr
Capital Cost
₹531.61 Cr
Start Date
20-08-2025
PCOD Date
-
Scheduled Completion
19-02-2028
Likely Completion
19-02-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-19 17:03:06
ASC Infratech Pvt. Ltd.
Physical progress stands at 17.6%. Financial utilization at 10.5%.
Project is on schedule or ahead of planned completion date.
Covers 3.3 km on 31, improving regional connectivity.
234 drone frames uploaded — real-time aerial monitoring is active for this project.
234 frames · NHAI surveillance footage · UPC N/08034/03004/BR