Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode

UPC: N/08034/03004/BR

Physical Progress

22.3%

Drone-monitored

Financial Progress

14.6%

Of awarded cost

Awarded Cost

₹368 Cr

Contract value

Length

3.3 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

582

Aerial captures

Project Progress

Physical Progress22.3%
Financial Progress14.6%

Stage

Under Construction (AD issued)

Due Date

19-02-2028

Likely Date

19-02-2028

Completion

22.3%

Physical Done

DoneRemaining

Project Timeline

Awarded

20-08-2025

Construction Started

20-08-2025

In Progress

Near Completion

-

Completed

19-02-2028

Physical vs Financial Progress

Project Details

UPC

N/08034/03004/BR

National Highway

31

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

3.3 km

Contractor

ASC Infratech Pvt. Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

582 frames

Last Flight

2026-08-26

Cost & Timeline

Awarded Cost

₹368.00 Cr

Capital Cost

₹531.61 Cr

Start Date

20-08-2025

PCOD Date

-

Scheduled Completion

19-02-2028

Likely Completion

19-02-2028

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-13 18:44:00

Contractor Profile

ASC Infratech Pvt. Ltd.

RO-Patna31HAM

Project Intelligence

1

Physical progress stands at 22.3%. Financial utilization at 14.6%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 3.3 km on 31, improving regional connectivity.

4

582 drone frames uploaded — real-time aerial monitoring is active for this project.

Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode is a National Highways Authority of India (NHAI) project on 31 in Bihar. The project has an awarded cost of ₹368.00 Cr and is currently ongoing with physical progress at 22.3%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

582 frames · NHAI surveillance footage · UPC N/08034/03004/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Construction of additional 3-Lane Bridge over River Ganga for connection between"?
Current physical progress: 22.3%. Financial progress: 14.6%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 19-02-2028. Likely completion: 19-02-2028.
QWho is the contractor for this NHAI highway project?
The contractor for Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode is ASC Infratech Pvt. Ltd.. The project is under RO-Patna and covers 3.3 km on 31.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹368.00 Crore. Total capital cost: ₹531.61 Crore. The project is on 31 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08034/03004/BR in NHAI?
UPC (Unique Project Code) N/08034/03004/BR refers to "Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922 in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode" — a National Highway project on 31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.