Physical Progress
38.9%
Drone-monitored
Financial Progress
18.0%
Of awarded cost
Awarded Cost
₹50 Cr
Contract value
Length
3.335 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
404
Aerial captures
Stage
Under Construction (AD issued)
Due Date
11-10-2025
Likely Date
31-08-2027
38.9%
Physical Done
Awarded
11-07-2024
Construction Started
11-07-2024
In Progress
Near Completion
-
Completed
31-08-2027
UPC
N/07016/01003/BR
National Highway
527D,27
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
3.335 km
Contractor
Amber Infraproject Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
404 frames
Last Flight
2026-02-24
Awarded Cost
₹49.80 Cr
Capital Cost
₹79.20 Cr
Start Date
11-07-2024
PCOD Date
-
Scheduled Completion
11-10-2025
Likely Completion
31-08-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:13:22
Amber Infraproject Pvt. Ltd.
Physical progress stands at 38.9%. Financial utilization at 18.0%.
Project is on schedule or ahead of planned completion date.
Covers 3.335 km on 527D,27, improving regional connectivity.
404 drone frames uploaded — real-time aerial monitoring is active for this project.
404 frames · NHAI surveillance footage · UPC N/07016/01003/BR