Original Cost
₹758 Cr
Baseline estimate
Revised Cost
₹758 Cr
Latest approved cost
Expenditure
₹266 Cr
Spent to date
Utilization
35.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹492 Cr
Budget left
Spent
₹266 Cr
Remaining
₹492 Cr
Total
₹758 Cr
Project Approved
Construction / Implementation
Original End Date
07/06/2026
Revised Completion
31/10/2027
Completed
Project is within original budget of ₹758 Cr — no cost escalation recorded.
Expenditure stands at ₹266 Cr, which is 35.0% of the revised project cost.
Remaining budget: ₹492 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.