CoalIPM · Central Project#400192

Tubed Coal Mine

Ministry of PowerJharkhand
Revised Cost: ₹1581 CrUtilization: 39.8%

Original Cost

₹1581 Cr

Baseline estimate

On budget

Revised Cost

₹1581 Cr

Latest approved cost

Expenditure

₹629 Cr

Spent to date

Utilization

39.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹952 Cr

Budget left

Budget Utilization

39.8%
0%25%50%75%100%

Spent

₹629 Cr

Remaining

₹952 Cr

Total

₹1581 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/05/2026

Revised Completion

30/12/2026

Completed

Project Details

Project Code400192
SectorCoal
MinistryMinistry of Power
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹1581 Cr
Revised Cost₹1581 Cr
Expenditure₹629 Cr
Original End Date31/05/2026
Revised Date30/12/2026

Project Intelligence

Project is within original budget of ₹1581 Cr — no cost escalation recorded.

Expenditure stands at ₹629 Cr, which is 39.8% of the revised project cost.

Remaining budget: ₹952 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Power.

Tubed Coal Mine is a centrally-funded infrastructure project under Ministry of Power, in the Coal sector. The original approved cost is ₹1581.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Tubed Coal Mine"?
Tubed Coal Mine is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Jharkhand. Original cost: ₹1581 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1581 Cr has not been significantly revised. Expenditure: ₹629 Cr (39.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Tubed Coal Mine is under the Ministry of Power in the Coal sector. Project code: 400192. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tubed Coal Mine is one of several Bihar projects tracked under the Coal sector on the IPM system.