TILABONI UG
Original Cost
₹749 Cr
Baseline estimate
Revised Cost
₹749 Cr
Latest approved cost
Expenditure
₹88 Cr
Spent to date
Utilization
11.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹661 Cr
Budget left
Budget Utilization
11.7%Spent
₹88 Cr
Remaining
₹661 Cr
Total
₹749 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2029
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹749 Cr — no cost escalation recorded.
Expenditure stands at ₹88 Cr, which is 11.7% of the revised project cost.
Remaining budget: ₹661 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.
TILABONI UG is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹749.00 Cr, later revised to ₹749.07 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "TILABONI UG"?
- TILABONI UG is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: West Bengal. Original cost: ₹749 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹749 Cr has not been significantly revised. Expenditure: ₹88 Cr (11.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- TILABONI UG is under the Ministry of Coal in the Coal sector. Project code: 400186. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. TILABONI UG is one of several Bihar projects tracked under the Coal sector on the IPM system.