Original Cost
₹154 Cr
Baseline estimate
Revised Cost
₹154 Cr
Latest approved cost
Expenditure
₹138 Cr
Spent to date
Utilization
89.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹16 Cr
Budget left
Spent
₹138 Cr
Remaining
₹16 Cr
Total
₹154 Cr
Project Approved
Construction / Implementation
Original End Date
08/11/2023
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹154 Cr — no cost escalation recorded.
Expenditure stands at ₹138 Cr, which is 89.5% of the revised project cost.
Remaining budget: ₹16 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.