Original Cost
₹29.3K Cr
Baseline estimate
Revised Cost
₹29.3K Cr
Latest approved cost
Expenditure
₹730 Cr
Spent to date
Utilization
2.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹28.6K Cr
Budget left
Spent
₹730 Cr
Remaining
₹28.6K Cr
Total
₹29.3K Cr
Project Approved
Construction / Implementation
Original End Date
31/01/2032
Revised Completion
Completed
Mega infrastructure project worth ₹29.3K Cr — among the largest central projects in Telangana.
Project is within original budget of ₹29.3K Cr — no cost escalation recorded.
Expenditure stands at ₹730 Cr, which is 2.5% of the revised project cost.
Remaining budget: ₹28.6K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.