Tapovan-Vishnugad HEP [4x130 MW]
Original Cost
₹2978 Cr
Baseline estimate
Revised Cost
₹10.9K Cr
Latest approved cost
Expenditure
₹7887 Cr
Spent to date
Utilization
72.3%
Of revised budget
Cost Status
+266.3%
+₹7929 Cr increase
Remaining
₹3020 Cr
Budget left
Budget Utilization
72.3%Spent
₹7887 Cr
Remaining
₹3020 Cr
Total
₹10.9K Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2978 Cr
Revised Cost
₹10.9K Cr
Increase
+₹7929 Cr
Escalation
+266.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2013
Revised Completion
31/07/2029
Completed
Project Details
Financial Summary
Project Intelligence
Mega infrastructure project worth ₹10.9K Cr — among the largest central projects in Uttarakhand.
Cost has increased by ₹7929 Cr (266.3%) from the original estimate of ₹2978 Cr.
Expenditure stands at ₹7887 Cr, which is 72.3% of the revised project cost.
Remaining budget: ₹3020 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Tapovan-Vishnugad HEP [4x130 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹2978.00 Cr, later revised to ₹10907.30 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Tapovan-Vishnugad HEP [4x130 MW]"?
- Tapovan-Vishnugad HEP [4x130 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Uttarakhand. Original cost: ₹2978 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2978 Cr and has been revised to ₹10907 Cr — a cost overrun of +266.3%. Expenditure to date: ₹7887 Cr (72.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Tapovan-Vishnugad HEP [4x130 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602185. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tapovan-Vishnugad HEP [4x130 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.