Original Cost
₹11.8K Cr
Baseline estimate
Revised Cost
₹12.5K Cr
Latest approved cost
Expenditure
₹6645 Cr
Spent to date
Utilization
53.0%
Of revised budget
Cost Status
+5.9%
+₹699 Cr increase
Remaining
₹5898 Cr
Budget left
Spent
₹6645 Cr
Remaining
₹5898 Cr
Total
₹12.5K Cr
Original Cost
₹11.8K Cr
Revised Cost
₹12.5K Cr
Increase
+₹699 Cr
Escalation
+5.9%
Project Approved
Construction / Implementation
Original End Date
31/05/2027
Revised Completion
31/05/2028
Completed
Mega infrastructure project worth ₹12.5K Cr — among the largest central projects in Odisha.
Cost has increased by ₹699 Cr (5.9%) from the original estimate of ₹11.8K Cr.
Expenditure stands at ₹6645 Cr, which is 53.0% of the revised project cost.
Remaining budget: ₹5898 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.