Talcher Thermal Power Station Stage III [2 x 660 MW] Expansion
Original Cost
₹11.8K Cr
Baseline estimate
Revised Cost
₹12.5K Cr
Latest approved cost
Expenditure
₹7147 Cr
Spent to date
Utilization
57.0%
Of revised budget
Cost Status
+5.9%
+₹699 Cr increase
Remaining
₹5396 Cr
Budget left
Budget Utilization
57.0%Spent
₹7147 Cr
Remaining
₹5396 Cr
Total
₹12.5K Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹11.8K Cr
Revised Cost
₹12.5K Cr
Increase
+₹699 Cr
Escalation
+5.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/05/2027
Revised Completion
31/05/2028
Completed
Project Details
Financial Summary
Project Intelligence
Mega infrastructure project worth ₹12.5K Cr — among the largest central projects in Odisha.
Cost has increased by ₹699 Cr (5.9%) from the original estimate of ₹11.8K Cr.
Expenditure stands at ₹7147 Cr, which is 57.0% of the revised project cost.
Remaining budget: ₹5396 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Talcher Thermal Power Station Stage III [2 x 660 MW] Expansion is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹11844.00 Cr, later revised to ₹12543.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Talcher Thermal Power Station Stage III [2 x 660 MW] Expansion"?
- Talcher Thermal Power Station Stage III [2 x 660 MW] Expansion is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Odisha. Original cost: ₹11844 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹11844 Cr and has been revised to ₹12543 Cr — a cost overrun of +5.9%. Expenditure to date: ₹7147 Cr (57.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Talcher Thermal Power Station Stage III [2 x 660 MW] Expansi is under the Ministry of Power in the Electricity Generation sector. Project code: 602961. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Talcher Thermal Power Station Stage III [2 x 660 MW] Expansi is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.