Original Cost
₹522 Cr
Baseline estimate
Revised Cost
₹522 Cr
Latest approved cost
Expenditure
₹325 Cr
Spent to date
Utilization
62.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹197 Cr
Budget left
Spent
₹325 Cr
Remaining
₹197 Cr
Total
₹522 Cr
Project Approved
Construction / Implementation
Original End Date
10/06/2026
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹522 Cr — no cost escalation recorded.
Expenditure stands at ₹325 Cr, which is 62.2% of the revised project cost.
Remaining budget: ₹197 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.