Super accelerated cooling system (Uniform Cooling) for high strength plates in Plate Mill at BSP
Original Cost
₹192 Cr
Baseline estimate
Revised Cost
₹192 Cr
Latest approved cost
Expenditure
₹79 Cr
Spent to date
Utilization
41.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹113 Cr
Budget left
Budget Utilization
41.2%Spent
₹79 Cr
Remaining
₹113 Cr
Total
₹192 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹192 Cr — no cost escalation recorded.
Expenditure stands at ₹79 Cr, which is 41.2% of the revised project cost.
Remaining budget: ₹113 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.
Super accelerated cooling system (Uniform Cooling) for high strength plates in Plate Mill at BSP is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹192.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Super accelerated cooling system (Uniform Cooling) for high strength plates in P"?
- Super accelerated cooling system (Uniform Cooling) for high strength plates in Plate Mill at BSP is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Chhattisgarh. Original cost: ₹192 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹192 Cr has not been significantly revised. Expenditure: ₹79 Cr (41.2% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Super accelerated cooling system (Uniform Cooling) for high is under the Ministry of Steel in the Steel sector. Project code: 944288. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Super accelerated cooling system (Uniform Cooling) for high is one of several Bihar projects tracked under the Steel sector on the IPM system.