Sunni Dam Hydro Electric Project [382 MW]
Original Cost
₹2615 Cr
Baseline estimate
Revised Cost
₹4555 Cr
Latest approved cost
Expenditure
₹1173 Cr
Spent to date
Utilization
25.8%
Of revised budget
Cost Status
+74.2%
+₹1940 Cr increase
Remaining
₹3382 Cr
Budget left
Budget Utilization
25.8%Spent
₹1173 Cr
Remaining
₹3382 Cr
Total
₹4555 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2615 Cr
Revised Cost
₹4555 Cr
Increase
+₹1940 Cr
Escalation
+74.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/04/2028
Revised Completion
31/12/2029
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1940 Cr (74.2%) from the original estimate of ₹2615 Cr.
Expenditure stands at ₹1173 Cr, which is 25.8% of the revised project cost.
Remaining budget: ₹3382 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Sunni Dam Hydro Electric Project [382 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹2615.00 Cr, later revised to ₹4555.49 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Sunni Dam Hydro Electric Project [382 MW]"?
- Sunni Dam Hydro Electric Project [382 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Himachal Pradesh. Original cost: ₹2615 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2615 Cr and has been revised to ₹4555 Cr — a cost overrun of +74.2%. Expenditure to date: ₹1173 Cr (25.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Sunni Dam Hydro Electric Project [382 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 611586. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sunni Dam Hydro Electric Project [382 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.