Electricity GenerationIPM · Central Project +74.2% overrun#611586

Sunni Dam Hydro Electric Project [382 MW]

Ministry of PowerHimachal Pradesh
Revised Cost: ₹4555 CrUtilization: 25.8%Overrun: +₹1940 Cr

Original Cost

₹2615 Cr

Baseline estimate

+74% overrun

Revised Cost

₹4555 Cr

Latest approved cost

Expenditure

₹1173 Cr

Spent to date

Utilization

25.8%

Of revised budget

Escalated

Cost Status

+74.2%

+₹1940 Cr increase

Remaining

₹3382 Cr

Budget left

Budget Utilization

25.8%
0%25%50%75%100%

Spent

₹1173 Cr

Remaining

₹3382 Cr

Total

₹4555 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2615 Cr

Revised Cost

₹4555 Cr

Increase

+₹1940 Cr

Escalation

+74.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/04/2028

Revised Completion

31/12/2029

Completed

Project Details

Project Code611586
SectorElectricity Generation
MinistryMinistry of Power
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2615 Cr
Revised Cost₹4555 Cr
Expenditure₹1173 Cr
Original End Date03/04/2028
Revised Date31/12/2029

Project Intelligence

Cost has increased by ₹1940 Cr (74.2%) from the original estimate of ₹2615 Cr.

Expenditure stands at ₹1173 Cr, which is 25.8% of the revised project cost.

Remaining budget: ₹3382 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Sunni Dam Hydro Electric Project [382 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹2615.00 Cr, later revised to ₹4555.49 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Sunni Dam Hydro Electric Project [382 MW]"?
Sunni Dam Hydro Electric Project [382 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Himachal Pradesh. Original cost: ₹2615 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2615 Cr and has been revised to ₹4555 Cr — a cost overrun of +74.2%. Expenditure to date: ₹1173 Cr (25.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Sunni Dam Hydro Electric Project [382 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 611586. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sunni Dam Hydro Electric Project [382 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.