Original Cost
₹2615 Cr
Baseline estimate
Revised Cost
₹4926 Cr
Latest approved cost
Expenditure
₹1098 Cr
Spent to date
Utilization
22.3%
Of revised budget
Cost Status
+88.4%
+₹2311 Cr increase
Remaining
₹3828 Cr
Budget left
Spent
₹1098 Cr
Remaining
₹3828 Cr
Total
₹4926 Cr
Original Cost
₹2615 Cr
Revised Cost
₹4926 Cr
Increase
+₹2311 Cr
Escalation
+88.4%
Project Approved
Construction / Implementation
Original End Date
03/04/2028
Revised Completion
31/12/2029
Completed
Cost has increased by ₹2311 Cr (88.4%) from the original estimate of ₹2615 Cr.
Expenditure stands at ₹1098 Cr, which is 22.3% of the revised project cost.
Remaining budget: ₹3828 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.