Original Cost
₹1694 Cr
Baseline estimate
Revised Cost
₹1694 Cr
Latest approved cost
Expenditure
₹1330 Cr
Spent to date
Utilization
78.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹364 Cr
Budget left
Spent
₹1330 Cr
Remaining
₹364 Cr
Total
₹1694 Cr
Project Approved
Construction / Implementation
Original End Date
23/04/2032
Revised Completion
Completed
Project is within original budget of ₹1694 Cr — no cost escalation recorded.
Expenditure stands at ₹1330 Cr, which is 78.5% of the revised project cost.
Remaining budget: ₹364 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.