Stamp Charge Battery No.12 Battery Proper at IISCO Steel Plant
Original Cost
₹2518 Cr
Baseline estimate
Revised Cost
₹2518 Cr
Latest approved cost
Expenditure
₹486 Cr
Spent to date
Utilization
19.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2032 Cr
Budget left
Budget Utilization
19.3%Spent
₹486 Cr
Remaining
₹2032 Cr
Total
₹2518 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/07/2028
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹2518 Cr — no cost escalation recorded.
Expenditure stands at ₹486 Cr, which is 19.3% of the revised project cost.
Remaining budget: ₹2032 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.
Stamp Charge Battery No.12 Battery Proper at IISCO Steel Plant is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹2518.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Stamp Charge Battery No.12 Battery Proper at IISCO Steel Plant"?
- Stamp Charge Battery No.12 Battery Proper at IISCO Steel Plant is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: West Bengal. Original cost: ₹2518 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹2518 Cr has not been significantly revised. Expenditure: ₹486 Cr (19.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Stamp Charge Battery No.12 Battery Proper at IISCO Steel Pla is under the Ministry of Steel in the Steel sector. Project code: 617338. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Stamp Charge Battery No.12 Battery Proper at IISCO Steel Pla is one of several Bihar projects tracked under the Steel sector on the IPM system.