CoalIPM · Central Project#400315

SONEPUR BAZARI EXPANSION OCP [

Ministry of CoalWest Bengal
Revised Cost: ₹5366 CrUtilization: 11.7%

Original Cost

₹5366 Cr

Baseline estimate

On budget

Revised Cost

₹5366 Cr

Latest approved cost

Expenditure

₹630 Cr

Spent to date

Utilization

11.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹4736 Cr

Budget left

Budget Utilization

11.7%
0%25%50%75%100%

Spent

₹630 Cr

Remaining

₹4736 Cr

Total

₹5366 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2029

Revised Completion

Completed

Project Details

Project Code400315
SectorCoal
MinistryMinistry of Coal
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹5366 Cr
Revised Cost₹5366 Cr
Expenditure₹630 Cr
Original End Date31/03/2029
Revised DateN/A

Project Intelligence

Project is within original budget of ₹5366 Cr — no cost escalation recorded.

Expenditure stands at ₹630 Cr, which is 11.7% of the revised project cost.

Remaining budget: ₹4736 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

SONEPUR BAZARI EXPANSION OCP [ is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹5366.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "SONEPUR BAZARI EXPANSION OCP ["?
SONEPUR BAZARI EXPANSION OCP [ is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: West Bengal. Original cost: ₹5366 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹5366 Cr has not been significantly revised. Expenditure: ₹630 Cr (11.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
SONEPUR BAZARI EXPANSION OCP [ is under the Ministry of Coal in the Coal sector. Project code: 400315. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. SONEPUR BAZARI EXPANSION OCP [ is one of several Bihar projects tracked under the Coal sector on the IPM system.