Original Cost
₹223 Cr
Baseline estimate
Revised Cost
₹223 Cr
Latest approved cost
Expenditure
₹141 Cr
Spent to date
Utilization
63.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹82 Cr
Budget left
Spent
₹141 Cr
Remaining
₹82 Cr
Total
₹223 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project is within original budget of ₹223 Cr — no cost escalation recorded.
Expenditure stands at ₹141 Cr, which is 63.1% of the revised project cost.
Remaining budget: ₹82 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.