SteelIPM · Central Project +12.6% overrun#709826

SCREENING PLANT-III AT KIRANDUL

Ministry of SteelChhattisgarh
Revised Cost: ₹3062 CrUtilization: 57.6%Overrun: +₹343 Cr

Original Cost

₹2719 Cr

Baseline estimate

+13% overrun

Revised Cost

₹3062 Cr

Latest approved cost

Expenditure

₹1764 Cr

Spent to date

Utilization

57.6%

Of revised budget

Escalated

Cost Status

+12.6%

+₹343 Cr increase

Remaining

₹1299 Cr

Budget left

Budget Utilization

57.6%
0%25%50%75%100%

Spent

₹1764 Cr

Remaining

₹1299 Cr

Total

₹3062 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2719 Cr

Revised Cost

₹3062 Cr

Increase

+₹343 Cr

Escalation

+12.6%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/01/2026

Revised Completion

31/07/2027

Completed

Project Details

Project Code709826
SectorSteel
MinistryMinistry of Steel
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹2719 Cr
Revised Cost₹3062 Cr
Expenditure₹1764 Cr
Original End Date31/01/2026
Revised Date31/07/2027

Project Intelligence

Cost has increased by ₹343 Cr (12.6%) from the original estimate of ₹2719 Cr.

Expenditure stands at ₹1764 Cr, which is 57.6% of the revised project cost.

Remaining budget: ₹1299 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Steel. Ministry: Ministry of Steel.

SCREENING PLANT-III AT KIRANDUL is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹2719.00 Cr, later revised to ₹3062.39 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "SCREENING PLANT-III AT KIRANDUL"?
SCREENING PLANT-III AT KIRANDUL is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Chhattisgarh. Original cost: ₹2719 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2719 Cr and has been revised to ₹3062 Cr — a cost overrun of +12.6%. Expenditure to date: ₹1764 Cr (57.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
SCREENING PLANT-III AT KIRANDUL is under the Ministry of Steel in the Steel sector. Project code: 709826. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. SCREENING PLANT-III AT KIRANDUL is one of several Bihar projects tracked under the Steel sector on the IPM system.