Original Cost
₹405 Cr
Baseline estimate
Revised Cost
₹405 Cr
Latest approved cost
Expenditure
₹36 Cr
Spent to date
Utilization
8.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹369 Cr
Budget left
Spent
₹36 Cr
Remaining
₹369 Cr
Total
₹405 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project is within original budget of ₹405 Cr — no cost escalation recorded.
Expenditure stands at ₹36 Cr, which is 8.9% of the revised project cost.
Remaining budget: ₹369 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.