Original Cost
₹472 Cr
Baseline estimate
Revised Cost
₹472 Cr
Latest approved cost
Expenditure
₹257 Cr
Spent to date
Utilization
54.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹215 Cr
Budget left
Spent
₹257 Cr
Remaining
₹215 Cr
Total
₹472 Cr
Project Approved
Construction / Implementation
Original End Date
14/06/2026
Revised Completion
30/09/2026
Completed
Project is within original budget of ₹472 Cr — no cost escalation recorded.
Expenditure stands at ₹257 Cr, which is 54.5% of the revised project cost.
Remaining budget: ₹215 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.