SteelIPM · Central Project#617255

Replacement of Converter Vessels, Trunnion Rings, Support System & Installation of Secondary Emission at Bhilai Steel Plant

Ministry of SteelChhattisgarh
Revised Cost: ₹472 CrUtilization: 57.7%

Original Cost

₹472 Cr

Baseline estimate

On budget

Revised Cost

₹472 Cr

Latest approved cost

Expenditure

₹273 Cr

Spent to date

Utilization

57.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹199 Cr

Budget left

Budget Utilization

57.7%
0%25%50%75%100%

Spent

₹273 Cr

Remaining

₹199 Cr

Total

₹472 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/06/2026

Revised Completion

30/09/2026

Completed

Project Details

Project Code617255
SectorSteel
MinistryMinistry of Steel
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹472 Cr
Revised Cost₹472 Cr
Expenditure₹273 Cr
Original End Date14/06/2026
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹472 Cr — no cost escalation recorded.

Expenditure stands at ₹273 Cr, which is 57.7% of the revised project cost.

Remaining budget: ₹199 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Steel. Ministry: Ministry of Steel.

Replacement of Converter Vessels, Trunnion Rings, Support System & Installation of Secondary Emission at Bhilai Steel Plant is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹472.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Replacement of Converter Vessels, Trunnion Rings, Support System & Installation "?
Replacement of Converter Vessels, Trunnion Rings, Support System & Installation of Secondary Emission at Bhilai Steel Plant is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Chhattisgarh. Original cost: ₹472 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹472 Cr has not been significantly revised. Expenditure: ₹273 Cr (57.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Replacement of Converter Vessels, Trunnion Rings, Support Sy is under the Ministry of Steel in the Steel sector. Project code: 617255. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Replacement of Converter Vessels, Trunnion Rings, Support Sy is one of several Bihar projects tracked under the Steel sector on the IPM system.