Rangit-IV HE Project [120 MW] executed by Jal Power Corporation Ltd. [JPCL] - A wholly owned subsidiary of NHPC Ltd. acquired through NCLT
Original Cost
₹938 Cr
Baseline estimate
Revised Cost
₹1828 Cr
Latest approved cost
Expenditure
₹1727 Cr
Spent to date
Utilization
94.5%
Of revised budget
Cost Status
+94.9%
+₹890 Cr increase
Remaining
₹101 Cr
Budget left
Budget Utilization
94.5%Spent
₹1727 Cr
Remaining
₹101 Cr
Total
₹1828 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹938 Cr
Revised Cost
₹1828 Cr
Increase
+₹890 Cr
Escalation
+94.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/05/2024
Revised Completion
30/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹890 Cr (94.9%) from the original estimate of ₹938 Cr.
Expenditure stands at ₹1727 Cr, which is 94.5% of the revised project cost.
Remaining budget: ₹101 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Rangit-IV HE Project [120 MW] executed by Jal Power Corporation Ltd. [JPCL] - A wholly owned subsidiary of NHPC Ltd. acquired through NCLT is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹938.00 Cr, later revised to ₹1828.11 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rangit-IV HE Project [120 MW] executed by Jal Power Corporation Ltd. [JPCL] - A"?
- Rangit-IV HE Project [120 MW] executed by Jal Power Corporation Ltd. [JPCL] - A wholly owned subsidiary of NHPC Ltd. acquired through NCLT is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Sikkim. Original cost: ₹938 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹938 Cr and has been revised to ₹1828 Cr — a cost overrun of +94.9%. Expenditure to date: ₹1727 Cr (94.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rangit-IV HE Project [120 MW] executed by Jal Power Corpora is under the Ministry of Power in the Electricity Generation sector. Project code: 605156. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rangit-IV HE Project [120 MW] executed by Jal Power Corpora is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.