Electricity GenerationIPM · Central Project +107.3% overrun#602184

Rammam-III HEPP [3x40 MW]

Ministry of PowerWest Bengal
Revised Cost: ₹2866 CrUtilization: 59.4%Overrun: +₹1484 Cr

Original Cost

₹1382 Cr

Baseline estimate

+107% overrun

Revised Cost

₹2866 Cr

Latest approved cost

Expenditure

₹1701 Cr

Spent to date

Utilization

59.4%

Of revised budget

Escalated

Cost Status

+107.3%

+₹1484 Cr increase

Remaining

₹1164 Cr

Budget left

Budget Utilization

59.4%
0%25%50%75%100%

Spent

₹1701 Cr

Remaining

₹1164 Cr

Total

₹2866 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1382 Cr

Revised Cost

₹2866 Cr

Increase

+₹1484 Cr

Escalation

+107.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2019

Revised Completion

30/09/2029

Completed

Project Details

Project Code602184
SectorElectricity Generation
MinistryMinistry of Power
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹1382 Cr
Revised Cost₹2866 Cr
Expenditure₹1701 Cr
Original End Date30/09/2019
Revised Date30/09/2029

Project Intelligence

Cost has increased by ₹1484 Cr (107.3%) from the original estimate of ₹1382 Cr.

Expenditure stands at ₹1701 Cr, which is 59.4% of the revised project cost.

Remaining budget: ₹1164 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Rammam-III HEPP [3x40 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹1382.00 Cr, later revised to ₹2865.56 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rammam-III HEPP [3x40 MW]"?
Rammam-III HEPP [3x40 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: West Bengal. Original cost: ₹1382 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1382 Cr and has been revised to ₹2866 Cr — a cost overrun of +107.3%. Expenditure to date: ₹1701 Cr (59.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rammam-III HEPP [3x40 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602184. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rammam-III HEPP [3x40 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.