Rammam-III HEPP [3x40 MW]
Original Cost
₹1382 Cr
Baseline estimate
Revised Cost
₹2866 Cr
Latest approved cost
Expenditure
₹1701 Cr
Spent to date
Utilization
59.4%
Of revised budget
Cost Status
+107.3%
+₹1484 Cr increase
Remaining
₹1164 Cr
Budget left
Budget Utilization
59.4%Spent
₹1701 Cr
Remaining
₹1164 Cr
Total
₹2866 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1382 Cr
Revised Cost
₹2866 Cr
Increase
+₹1484 Cr
Escalation
+107.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/09/2019
Revised Completion
30/09/2029
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1484 Cr (107.3%) from the original estimate of ₹1382 Cr.
Expenditure stands at ₹1701 Cr, which is 59.4% of the revised project cost.
Remaining budget: ₹1164 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Rammam-III HEPP [3x40 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹1382.00 Cr, later revised to ₹2865.56 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rammam-III HEPP [3x40 MW]"?
- Rammam-III HEPP [3x40 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: West Bengal. Original cost: ₹1382 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1382 Cr and has been revised to ₹2866 Cr — a cost overrun of +107.3%. Expenditure to date: ₹1701 Cr (59.4% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rammam-III HEPP [3x40 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602184. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rammam-III HEPP [3x40 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.