Pune Metro Rail Project Phase-2 Line-4 Kharadi to Khadakwasla with Spur Line 4A Nal Stop - Warje - Manikbaug
Original Cost
₹9858 Cr
Baseline estimate
Revised Cost
₹9858 Cr
Latest approved cost
Expenditure
₹10 Cr
Spent to date
Utilization
0.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹9848 Cr
Budget left
Budget Utilization
0.1%Spent
₹10 Cr
Remaining
₹9848 Cr
Total
₹9858 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2030
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹9858 Cr — no cost escalation recorded.
Expenditure stands at ₹10 Cr, which is 0.1% of the revised project cost.
Remaining budget: ₹9848 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.
Pune Metro Rail Project Phase-2 Line-4 Kharadi to Khadakwasla with Spur Line 4A Nal Stop - Warje - Manikbaug is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Urban Public Transport sector. The original approved cost is ₹9858.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Pune Metro Rail Project Phase-2 Line-4 Kharadi to Khadakwasla with Spur Line 4A "?
- Pune Metro Rail Project Phase-2 Line-4 Kharadi to Khadakwasla with Spur Line 4A Nal Stop - Warje - Manikbaug is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Urban Public Transport. State: Maharashtra. Original cost: ₹9858 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹9858 Cr has not been significantly revised. Expenditure: ₹10 Cr (0.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Pune Metro Rail Project Phase-2 Line-4 Kharadi to Khadakwasl is under the Ministry of Housing & Urban Affairs in the Urban Public Transport sector. Project code: 618985. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pune Metro Rail Project Phase-2 Line-4 Kharadi to Khadakwasl is one of several Bihar projects tracked under the Urban Public Transport sector on the IPM system.