Aviation & Aviation InfrastructureIPM · Central Project#611440

Procurment of 30 Nos ACFTs of WT Capacity 10KL at Various Airports

Ministry of Civil AviationAndhra Pradesh
Revised Cost: ₹215 CrUtilization: 48.8%

Original Cost

₹215 Cr

Baseline estimate

On budget

Revised Cost

₹215 Cr

Latest approved cost

Expenditure

₹105 Cr

Spent to date

Utilization

48.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹110 Cr

Budget left

Budget Utilization

48.8%
0%25%50%75%100%

Spent

₹105 Cr

Remaining

₹110 Cr

Total

₹215 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2025

Revised Completion

Completed

Project Details

Project Code611440
SectorAviation & Aviation Infrastructure
MinistryMinistry of Civil Aviation
StateAndhra Pradesh
Data Month2025-07

Financial Summary

Original Cost₹215 Cr
Revised Cost₹215 Cr
Expenditure₹105 Cr
Original End Date30/06/2025
Revised DateN/A

Project Intelligence

Project is within original budget of ₹215 Cr — no cost escalation recorded.

Expenditure stands at ₹105 Cr, which is 48.8% of the revised project cost.

Remaining budget: ₹110 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.

Procurment of 30 Nos ACFTs of WT Capacity 10KL at Various Airports is a centrally-funded infrastructure project under Ministry of Civil Aviation, in the Aviation & Aviation Infrastructure sector. The original approved cost is ₹215.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Procurment of 30 Nos ACFTs of WT Capacity 10KL at Various Airports"?
Procurment of 30 Nos ACFTs of WT Capacity 10KL at Various Airports is a centrally-funded infrastructure project under the Ministry of Civil Aviation, tracked through the Investment Project Monitoring (IPM) system. Sector: Aviation & Aviation Infrastructure. State: Andhra Pradesh. Original cost: ₹215 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹215 Cr has not been significantly revised. Expenditure: ₹105 Cr (48.8% of cost). Data as of 2025-07.
QWhich ministry is responsible for this project?
Procurment of 30 Nos ACFTs of WT Capacity 10KL at Various Ai is under the Ministry of Civil Aviation in the Aviation & Aviation Infrastructure sector. Project code: 611440. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Procurment of 30 Nos ACFTs of WT Capacity 10KL at Various Ai is one of several Bihar projects tracked under the Aviation & Aviation Infrastructure sector on the IPM system.