Pollution Abatement Works for River Kali Meerut under Meerut Municipality Interception & Diversion with STP
Original Cost
₹691 Cr
Baseline estimate
Revised Cost
₹691 Cr
Latest approved cost
Expenditure
₹35 Cr
Spent to date
Utilization
5.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹656 Cr
Budget left
Budget Utilization
5.0%Spent
₹35 Cr
Remaining
₹656 Cr
Total
₹691 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2024
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹691 Cr — no cost escalation recorded.
Expenditure stands at ₹35 Cr, which is 5.0% of the revised project cost.
Remaining budget: ₹656 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Department of Water Resources, River Development & GR.
Pollution Abatement Works for River Kali Meerut under Meerut Municipality Interception & Diversion with STP is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Waste & Water sector. The original approved cost is ₹691.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Pollution Abatement Works for River Kali Meerut under Meerut Municipality Inter"?
- Pollution Abatement Works for River Kali Meerut under Meerut Municipality Interception & Diversion with STP is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Uttar Pradesh. Original cost: ₹691 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹691 Cr has not been significantly revised. Expenditure: ₹35 Cr (5.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Pollution Abatement Works for River Kali Meerut under Meerut is under the Department of Water Resources, River Development & GR in the Waste & Water sector. Project code: 616605. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pollution Abatement Works for River Kali Meerut under Meerut is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.