NMDC Slurry Pipeline Project Phase-1
Original Cost
₹2907 Cr
Baseline estimate
Revised Cost
₹5427 Cr
Latest approved cost
Expenditure
₹3685 Cr
Spent to date
Utilization
67.9%
Of revised budget
Cost Status
+86.7%
+₹2520 Cr increase
Remaining
₹1742 Cr
Budget left
Budget Utilization
67.9%Spent
₹3685 Cr
Remaining
₹1742 Cr
Total
₹5427 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2907 Cr
Revised Cost
₹5427 Cr
Increase
+₹2520 Cr
Escalation
+86.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/06/2023
Revised Completion
15/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹2520 Cr (86.7%) from the original estimate of ₹2907 Cr.
Expenditure stands at ₹3685 Cr, which is 67.9% of the revised project cost.
Remaining budget: ₹1742 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.
NMDC Slurry Pipeline Project Phase-1 is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹2907.00 Cr, later revised to ₹5427.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "NMDC Slurry Pipeline Project Phase-1"?
- NMDC Slurry Pipeline Project Phase-1 is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Chhattisgarh. Original cost: ₹2907 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2907 Cr and has been revised to ₹5427 Cr — a cost overrun of +86.7%. Expenditure to date: ₹3685 Cr (67.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- NMDC Slurry Pipeline Project Phase-1 is under the Ministry of Steel in the Steel sector. Project code: 706811. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. NMDC Slurry Pipeline Project Phase-1 is one of several Bihar projects tracked under the Steel sector on the IPM system.