Original Cost
₹2907 Cr
Baseline estimate
Revised Cost
₹5427 Cr
Latest approved cost
Expenditure
₹3617 Cr
Spent to date
Utilization
66.6%
Of revised budget
Cost Status
+86.7%
+₹2520 Cr increase
Remaining
₹1810 Cr
Budget left
Spent
₹3617 Cr
Remaining
₹1810 Cr
Total
₹5427 Cr
Original Cost
₹2907 Cr
Revised Cost
₹5427 Cr
Increase
+₹2520 Cr
Escalation
+86.7%
Project Approved
Construction / Implementation
Original End Date
30/06/2023
Revised Completion
31/05/2026
Completed
Cost has increased by ₹2520 Cr (86.7%) from the original estimate of ₹2907 Cr.
Expenditure stands at ₹3617 Cr, which is 66.6% of the revised project cost.
Remaining budget: ₹1810 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.